HomeMy WebLinkAbout2009-08-06 - Planning-Engineering-Operations Committee Meeting Minutes
MINUTES OF THE
YORBA LINDA WATER DISTRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
August 6, 2009
A meeting of the Planning-Engineering-Operations Committee was called to order by
Director Mills at 4:00 p.m. The meeting was held at the District's Administrative Office
at 1717 E Miraloma Ave, Placentia CA 92870.
COMMITTEE STAFF
Director William R. Mills, Chair Ken Vecchiarelli, General Manager
Director Paul R. Armstrong Steve Conklin, Engineering Manager
Lee Cory, Operations Manager
Ken Mendum, Ops Superintendent
John DeCriscio, Chief Plant Operator
1. PUBLIC COMMENTS
None.
2. ACTION CALENDAR
2.1. Proposed Casino Ridge Project, Tract 16488
Mr. Bob King of the King Family Trust, along with Mr. Mark Guithues and
Mr. Gordon Thomson were present to discuss the issues regarding the
proposed Casino Ridge Project. Mr. Vecchiarelli provided background
concerning this and adjacent projects. Mr. King described the proposed
project and a handout was provided by Mr. Thomson with talking points for
discussion. A discussion followed concerning the issues of water pressure
for fire service and residential needs, and meeting water storage
requirements. At the conclusion of the discussion, the Committee asked
that staff continue to work on these items with the King Family
representatives, and to return at a later date to the PEO Committee with
proposed actions for consideration.
2.2. Terms and Conditions for Water and Sewer Service with Dentino
Properties
Mr. Conklin described the proposed improvements and terms and
conditions. He also pointed out minor changes in the project description
and the terms and conditions that were requested by the property owner.
Following discussion, the Committee supported staff's recommendation
for approval of the Terms and Conditions, with the minor revisions as
described.
2.3. Preparation of an Asset Management Plan
Mr. Conklin described the elements of the proposed asset management
plan and the resulting product that will assist the District in planning for the
future. He went on to describe the proposals received from consultants,
and the proposal review process for the preparation of the Asset
1
Management Plan. Following discussion, the Committee supported staff's
recommendation for award of the Professional Services Agreement to
Carollo Engineers, for a fee not to exceed $112,000, for the preparation of
the Asset Management Plan.
2.4. Proposed Installation of Solar Panels on Spring View Reservoir
Mr. Conklin described the proposed plan to install a small-scale (30
kilowatt) solar power generation facility at the Spring View Reservoir site
as a means to determine the actual cost of constructing and operating
solar power facilities, before considering large-scale facilities for the
District. He reported that RFPs were sent to five solar providers and three
proposals were received to design and install a complete and operable
unit. Following discussion, the Committee supported staff's
recommendation to award the project to the low-bidder, Akeena Solar,
Inc., for a cost not to exceed $227,489.
2.5 Proposed Change Order to Well 12 Testing Contract
Mr. Vecchiarelli requested that this item be added to the agenda for
consideration by the Committee, so that work can proceed on Well 12 to
restore it to service. The Committee agreed with staff's request to add this
to the agenda for consideration. Mr. Conklin described the testing program
recently completed on Well 12 and the recommendations made by CDM,
the District's consultant, for modifications to restore it to service. He
reported that General Pump, the service company that performed the
testing, was requested by staff to provide a cost proposal for the
modifications. He indicated that staff reviewed the cost proposal and
recommends approval. After discussion, the Committee supported staff's
recommendation for approval of Change Order No. 1 in the amount of
$56,973.39 for General Pump Company to provide improvements to Well
12.
3. DISCUSSION ITEMS
3.1. Completion of Construction of Bastanchury 18" and 36" Water Mains
Mr. Conklin reported that the above work was completed by Shapell's
contractor, as the fifth and final reach of the project, totaling approximately
six miles of pipeline from Gardenia Reservoir to Fairmont Reservoir. The
total cost to the District was $1,010,185 for upsizing of elements of the
project to accommodate future growth and needs.
3.2. Monthly Groundwater Production and Purchased Water Report
Mr. DeCriscio reported on water production for July 2009, noting that it
was 9.6% under the budgeted amount. He also noted that the July 2009
production was the lowest July in the last eight years.
3.3. Monthly Preventative Maintenance Program Report
Mr. Mendum discussed the information presented in the PM Report,
noting that Maintenance Department staff worked extensively in July on
the painting of fire hydrants and the upgrading of water system sampling
2
stations. The latter work was at the request of the Engineering
Department, to minimize water discharge to the street and sidewalk when
sampling station service lines are purged before weekly sample collection.
With the completion of these tasks, Mr. Mendum stated he anticipates no
problem getting back on schedule on maintenance items that fell below
monthly goals and objectives.
3.4. Monthly MWDOC Managers Meeting Summary Report
Mr. Vecchiarelli reported that Mr. Grady attended the above meeting and
participated in the discussion on the preparation of the response to the
Grand Jury.
3.5. Monthly OC Groundwater Producers Meeting Summary Report
Mr. Conklin reported that this meeting had been cancelled.
3.6. Status Report on Capital Projects in Progress
Mr. Conklin briefed the Committee on projects in the monthly status report.
3.7. Future Agenda Items and Staff Tasks
None.
4. ADJOURNMENT
4.1. The meeting was adjourned at 5:53 p.m. The next regular meeting of the
Planning-Engineering-Operations Committee will be held September 3,
2009 at 4:00 p.m.
3