HomeMy WebLinkAbout2009-12-03 - Planning-Engineering-Operations Committee Meeting Minutes
MINUTES OF THE
YORBA LINDA WATER DISTRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
December 3, 2009
A meeting of the Planning-Engineering-Operations Committee was called to order by
Director Mills at 4:00 p.m. The meeting was held at the District's Administrative Office
at 1717 E Miraloma Ave, Placentia CA 92870.
COMMITTEE STAFF
Director William R. Mills, Chair Ken Vecchiarelli, General Manager
Director Michael J. Beverage, Alternate Steve Conklin, Engineering Manager
Lee Cory, Operations Manager
John DeCriscio, Chief Plant Operator
Joe Polimino, Project Engineer
1. PUBLIC COMMENTS
None.
2. ACTION CALENDAR
2.1. Change Order No. 1 for San Antonio Pressure Reducing Station Upgrade
Project.
Mr. Conklin reported that the project construction is essentially complete,
with electrical and communications connections remaining; the facility is
operating in manual mode and delivering water to the new 706 Zone.
Construction change order items were presented. Following discussion,
the Committee supported staff's recommendation for approval of Change
Order No. 1 in the amount of $20,566.73.
2.2. Change Order No. 1 for Lakeview Sewer Lift Station Rehabilitation
Project.
Mr. Conklin reported that project construction is complete and that the
completely refurbished lift station is in full operation. Construction change
order items were presented, including additional cost to operate the by-
pass pumping system for five extra days because Edison Company could
not respond and complete the final power hookup on the day scheduled,
due to the need to respond to an emergency. Following discussion, the
Committee supported Staff's recommendation for approval of Change
Order No. 1 in the amount of $47,302, and requested that Staff contact
Edison to request reimbursement for extra costs due to Edison's delayed
response.
2.3. Change Order No. 1 for Zone Reconfiguration Project.
Mr. Conklin reported that project construction is essentially complete and
that higher pressure water service is now being provided to approximately
800 homes in the Zone 4 Eastlake area; an additional area of
approximately 100 homes to the northwest will receive higher pressure
1
water service by February 1, 2010. Construction change order items were
presented including a request for $150,000 for added cost and lost
production due to the need to move all construction equipment to and from
the work site each work day, rather than secure and barricade it along the
roadway. This requirement was established by the City of Yorba Linda on
the contractor after award of the contract as a condition of the City's
encroachment permit.
Other extras were also described, almost all of which were due to conflicts
from existing unmarked or unknown pipes or appurtenances that delayed
work or required rerouting of the new pipeline. Mr. Conklin noted that
Staff is requesting reimbursement from The Gas Company and AT&T for
the mismarking of their lines that resulted in extra work claims by the
contractor. Following discussion, the Committee recommended approval
of change order items totaling $75,027.39, but did not approve the request
for $150,000 for extra daily mobilization and lost production. For this latter
item, the Committee recommended further investigation and additional
negotiations with the contractor prior to bringing options back to the
Committee for further consideration in January.
2.4. Sewer Master Plan Update
Mr. Conklin reported proposals were received from five consultants for the
preparation of a Sewer Master Plan Update. He described the proposal
evaluation process used by the three-member review team to score and
rank the proposals based on technical merit. He noted that following the
technical evaluation and ranking, the separate envelopes submitted by
each firm presenting the proposed fee were opened and examined.
Following discussion, the Committee supported Staff's recommendation,
based on technical merit and a competitive fee, that award be made to ID
Modeling for a fee not to exceed $300,210.
3. DISCUSSION ITEMS
3.1. Monthly Groundwater Production and Purchased Water Report.
Mr. DeCriscio reported on the water use for November, noting that we
were 14.4% above our projection for the month, and that cumulatively we
are 3.1 % below our projection year to date and 13.1 % below our use from
last year, July through November. He noted that our groundwater
production is on track with our plan for the year.
3.2. Monthly Preventative Maintenance Program Report.
Mr. Cory reported on the status of our PM activities and noted that we had
to divert concentrated resources outside the PM program to support valve
repairs and shutdown coordination activities for system tie-ins related to
the Zone Reconfiguration Project. Mr. Cory reported with this project
completed, we are able to refocus those resources to specific PM
activities that are running slightly below target.
2
3.3. Monthly OC Groundwater Producers Meeting Summary Report
Mr. Conklin reported on the minutes from the November Groundwater
Producers Meeting. He noted the discussion that took place on the YLWD
annexation request. Mr. Vecchiarelli indicated that the City of Anaheim
may combine its annexation request with ours, with both carried forward
together. However, we have not yet seen the formal letter of request from
the City to OCWD. Regardless, YLWD will continue to push forward with
these efforts.
3.4. Status Report on Capital Projects in Progress
Mr. Conklin gave a comprehensive update on the status of capital projects
in planning, design and construction.
3.5. Future Agenda Items and Staff Tasks
None.
4. ADJOURNMENT
4.1. The meeting was adjourned at 5:30 p.m. The next regular meeting of the
Planning-Engineering-Operations Committee will be held January 7, 2010
at 4:00 p.m.
3