HomeMy WebLinkAbout2010-04-01 - Planning-Engineering-Operations Committee Meeting Minutes
MINUTES OF THE
YORBA LINDA WATER DISTRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
April 1, 2010
A meeting of the Planning-Engineering-Operations Committee was called to order by
Director Mills at 4:00 p.m. The meeting was held at the District's Administrative Office
at 1717 E Miraloma Ave, Placentia CA 92870.
COMMITTEE STAFF
Director William R. Mills, Chair Ken Vecchiarelli, General Manager
Director John W. Summerfield Steve Conklin, Engineering Manager
Lee Cory, Operations Manager
John DeCriscio, Chief Plant Operator
1. PUBLIC COMMENTS
None.
2. DISCUSSION ITEMS
2.1. Monthly Groundwater Production and Purchased Import Water Report
Mr. DeCriscio reported on water production in March, noting that we have
met our MWD CUP obligation and, at the request of MWDOC, are
planning to take an additional 600 AF of CUP water between now and the
end of June, with no financial impact to YLWD. This will be the last of the
MWD water in the basin stored under the CUP. Overall, the District's
water demand is 6.9% under the target reduction of 10% for conservation.
2.2. Monthly Preventative Maintenance Program Report
Mr. Cory reported on the status of the PM Program through March. He
noted that we are on target to meet our PM goals for the year, except for
sewer televising. We fell behind because equipment was out for repair,
though now back in operation and catching up. The budget for FY 10-11
includes a spare crawler unit for the video unit, which should significantly
reduce equipment down-time in the future.
3. ACTION CALENDAR
3.1. Urgent Pipeline Replacement Project, Ohio Street North of Oriente Drive
Mr. Vecchiarelli and Mr. Cory reported on the pipeline failure on Ohio
Street on March 27 and the process to restore service. Mr. Vecchiarelli
noted that the pipeline along Ohio was constructed in sections between
1938 and 1948 and has had several breaks over the last 10 years. Due to
the need for continuing repairs and the risk liability, moving forward with
immediate replacement is recommended by staff. Following discussion,
the Committee supported staff recommendation to move forward
immediately to retain an engineering consultant for design of the
1
replacement water line in Ohio Street from Yorba Linda Boulevard
northerly to its terminus at J & J Lane, approximately 3400 feet.
3.2. Well 5 Pump Installation for the Well Rehabilitation Project
Mr. Conklin reported that rehabilitation testing of Well 5 has been
completed and quotes were solicited for the installation of a new pump.
He also reported that a low-bid of $51,249 was received from Layne
Christensen Company, which was reviewed and accepted by staff. In
order to minimize lost well-production and the cost impacts of purchasing
additional import water, staff directed Layne to commence work after
completion of contract documents. Following discussion, the Committee
supported staff recommendation that the Board ratify execution of the
agreement with Layne Christensen.
3.3. Mitigated Negative Declaration, Highland Booster Station Replacement
Project
Mr. Conklin reported that the initial environmental study in conformance
with CEQA was completed by MWH, the District's consultant for the
Highland Booster Station Project. The analysis indicates that the
proposed project can be implemented without causing significant adverse
environmental impacts with incorporation of mitigation measures
summarized in the Mitigation Monitoring and Reporting Plan prepared for
the project. Following discussion, the Committee supported staff
recommendation that the Board adopt the Plan, find that the Project with
incorporation of the mitigation measures, will not have a significant effect
on the environment, and authorize staff to file a Notice of Determination
for the project.
3.4. Brand Name Requirement for Highland Booster Station Project
Mr. Conklin reported that as part of the design process for the subject
project, staff determined that several key design components and
manufactured parts from specific suppliers were desired in order to match
other products already in use in the District's water system. Following
direction of legal counsel, staff prepared a report setting forth the reasons
for requiring brand name components and parts, which was presented to
the Committee for review and discussion. Following that discussion, the
Committee supported staff's recommendation that the Board approve
brand-name requirements for the project for the items listed in the staff
report.
4. DISCUSSION ITEMS (Continued)
4.1. Monthly Groundwater Producers Meeting Report
Mr. Conklin reported on the items discussed and presented at the March
10 Groundwater Producers Meeting.
4.2. Capital Improvement and Replacement Projects Budget
Mr. Conklin presented a copy of the Five Year CIP approved by the Board
for the FY 2009-10 Budget and provided a copy showing project progress
2
in the last year. The latter table showed expected expenditures on CIP
projects through June 2010, and proposed projects and budgets for the
next three fiscal years. The table showed the status of projects added in
FY 2009-10, and new projects proposed for FY 2010-11, with the newly
proposed projects being pipeline replacement projects, totaling an
estimated $1.85 million. The Committee reviewed the project information
with staff and briefly discussed funding mechanisms. Mr. Vecchiarelli
noted that the issue of funding will be discussed at the Finance-
Accounting Committee meeting and following Board meetings.
4.3. Status Report on Capital Projects in Progress
Mr. Conklin reported on projects in planning, design and construction.
4.4. Future Agenda Items and Staff Tasks
None.
5. ADJOURNMENT
5.1. The meeting was adjourned at 5:30 p.m. The next regular meeting of the
Planning-Engineering-Operations Committee will be held May 6, 2010 at
4:00 p.m.
3