HomeMy WebLinkAbout2010-05-06 - Planning-Engineering-Operations Committee Meeting Agenda Packet
Yorba Linda
Water District
AGENDA
YORBA LINDA WATER DISTRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
Thursday, May 6, 2010, 4:00 PM
1717 E Miraloma Ave, Placentia CA 92870
COMMITTEE STAFF
Director William R. Mills, Chair Ken Vecchiarelli, General Manager
Director Michael J. Beverage, Alternate Steve Conklin, Engineering Manager
Lee Cory, Operations Manager
Ken Mendum, Operations Superintendent
John DeCriscio, Chief Plant Operator
1. PUBLIC COMMENTS
Any individual wishing to address the committee is requested to identify themselves and state the matter on
which they wish to comment. If the matter is on this agenda, the committee Chair will recognize the individual for
their comment when the item is considered. No action will be taken on matters not listed on this agenda.
Comments are limited to matters of public interest and matters within the jurisdiction of the Water District.
Comments are limited to five minutes.
2. DISCUSSION ITEMS
This portion of the agenda is for matters such as technical presentations, drafts of proposed policies, or similar
items for which staff is seeking the advice and counsel of the Committee members. This portion of the agenda
may also include items for information only.
2.1. Monthly Groundwater Production and Purchased Import Water Report (To be provided
at the meeting.)
2.2. Monthly Preventative Maintenance Program Report
2.3. Monthly Groundwater Producers Meeting Report
2.4. Status Report on Capital Projects in Progress
2.5. Second Version of Capital Improvement and Replacement Projects Budget
2.6. Future Agenda Items and Staff Tasks
3. ADJOURNMENT
3.1. The next regular meeting of the Planning-Engineering-Operations Committee will be held
June 3, 2010 at 4:00 p.m.
Items Distributed to the Committee Less Than 72 Hours Prior to the Meeting
Pursuant to Government Code section 54957.5, non-exempt public records that relate to open session agenda items
and are distributed to a majority of the Committee less than seventy-two (72) hours prior to the meeting will be available
for public inspection in the lobby of the District's business office located at 1717 E. Miraloma Avenue, Placentia, CA
92870, during regular business hours. When practical, these public records will also be made available on the District's
internet website accessible at http://www.ylwd.com/.
Accommodations for the Disabled
Any person may make a request for a disability-related modification or accommodation needed for that person to be
able to participate in the public meeting by telephoning the Executive Secretary at 714-701-3020, or writing to Yorba
Linda Water District, P.O. Box 309, Yorba Linda, CA 92885-0309. Requests must specify the nature of the disability and
the type of accommodation requested. A telephone number or other contact information should be included so the
District staff may discuss appropriate arrangements. Persons requesting a disability-related accommodation should
make the request with adequate time before the meeting for the District to provide the requested accommodation.
ITEM NO. 2.1
AGENDA REPORT
Meeting Date: May 6, 2010
Subject: Monthly Groundwater Production and Purchased Import Water Report (To be
provided at the meeting.)
ATTACHMENTS:
Nam
GW Production and Purchased Water Report.pdf GW Production and Purchased Water Report Backup Material
YLWD SOURCE WATER SUMMARY
Fiscal Year 2009-10
TOTAL MONTHLY YTD BUDGET
GW IMPORT CUP DEMAND GW GW (Demand Est.) DELTA
MONTH (AF) (AF) (AF) (AF) (AF)
Jul-09 192.2 933.4 1,212.0 2,337.6 8.2% 8.2% 2,585.9 -9.6%
Aug-09 377.8 961.3 979.8 2,318.9 16.3% 12.2% 2,544.1 -8.9%
Sep-09 1,309.4 911.5 2,220.9 59.0% 27.3% 2,232.2 -0.5%
Oct-09 1,205.4 617.6 1,823.0 66.1% 35.5% 1,882.8 -3.2%
Nov-09 1,026.4 673.9 1,700.3 60.4% 39.5% 1,487.4 14.3%
Dec-09 793.9 369.4 1,163.3 68.2% 42.4% 1,338.0 -13.1%
Jan-10 806.9 308.0 1,114.9 72.4% 45.1% 1,166.6 -4.4%
Feb-10 564.5 109.5 674.0 83.8% 47.0% 1,116.1 -39.6%
Mar-10 576.2 370.5 289.1 1,235.8 46.6% 47.0% 1,322.6 -6.6%
Apr-10 665.4 749.8 58.7 1,473.9 45.1% 46.8% 1,654.3 10.9%
May-10 - 2,188.2
Jun-10 - 2,451.9
FYTD 7,518.1 6,004.9 2,539.6 16,062.6 46.8% 17,329.9
Allowable GW (YTD) 7,489.0 (AF)
CUP Obligation FY 2009-10 2,193.0 (AF)
Monthly CUP Pumping (AF) 58.7 (AF)
YTD CUP Pumping (AF) 2,539.6 (AF)
YTD CUP Achieved 115.8%
GROUNDWATER PERCENTAGE
85.0%
75.0%
65.0%
55.0%
45.0%
35.0%
25.0%
MONTHLY GW )
15.0% -8dYTD GW
BPP GOAL 46.6%
5.0%
O°~ 00 00 00 O°~ O°~ ,~O NF) NCO NCO NCO NQ)
Qua' ~~Q ova ~oJ Oro )ate ~ac PQc ~a~
Month
WATER SUPPLY
FY 2009-2010
April 2010 Water Supply
CUP
4.0%
GW
45.1%
IMPORT
50.9%
2009-2010 YTD Water Supply
CUP
15.8%
GW
46.8%
IMPORT
37.4% GW BPP GOAL
46.6%
3,500
1I
2,500
cz:7 2,000
Q
N
E
O
O
> 1,500
1,000
500
Total Water Use
Q%, o°' o� o�' o�' o� o�' o�' o� o�' orb o% o° ^° o�' o�' '.° o%' o°' �.° o�' o°' �.° � o%' le �.° o% o° ^°
F e, F q, F �
� ��
Month
■09 -10 GW
009 -10 IMPORT
Monthly Average Mean Temperature ( °F)
008-09 GW
72.7 74.8 008 -09 IMPORT
■07 -08 GW
72.2 73.6
007 -08 IMPORT
70.5
70.4
69.8
74.0
74.3
64.0
67.4
74.1 65.9
63.3
66.4
61.0
65.4
61.6
66.1
60.1
62.6
58'2
62.6
59.3
54.0
60.2
55.8
54.3 55.0
58.2 55.4
56.3
57.2
Q%, o°' o� o�' o�' o� o�' o�' o� o�' orb o% o° ^° o�' o�' '.° o%' o°' �.° o�' o°' �.° � o%' le �.° o% o° ^°
F e, F q, F �
� ��
Month
22,000
20,000
18,000
16,000
14,000
U-
12,000
m
E
0 10,000
8,000
6,000
4,000
2,000
0
Jul -09
2009 -2010 YTD Water Supply
Budgeted Total GW + Import
—00-Actual Total GW + Import
BPP GW Goal 46.6%
Actual GW Production
-000,
Aug -09 Sep -09 Oct -09 Nov -09 Dec -09 Jan -10 Feb -10 Mar -10 Apr -10 May -10 Jun -10
Month
ITEM NO. 2.2
AGENDA REPORT
Meeting Date: May 6, 2010
Subject: Monthly Preventative Maintenance Program Report
ATTACHMENTS:
Name: cv, i~a$icri: a ype:
2009-10 PM Report.pdt 2009-10 PM Report Backup Material
PM PROGRAM
2009/2010
Fiscal 2009 -10 1 JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN
Percent of target 8% 17% 25% 33% 42% 50% 58% 67% 75% 92% 100%
HYDRANTS (3,881) Target; all hydrants to be serviced annually.
INSPECTED THIS MONTH 0
5401
3541
131 130
2061
9921
4201
5851
5231
1
INSPECTED THIS YEAR 0
5401
894
1,025 1,155
1,361
1 2,353
1 2,773
1 3,358
1 3,881
% OF TOTAL 0.0%
14.0%1
23.0%1
26.4% 29.8%
35.0%1
60.6%1
71.5%1
86.5%
VALVES (10,706/2= 5,353) Target; all valves to be operated every two years
OPERATED THIS MONTH 242
2941
4561
5751
326 463
2271
5201
290
1 658
OPERATED THIS YEAR 242
5361
9921
1,5671
1,893 2,356
2,5831
3,1031
3,393
1 4,051
% OF TOTAL 4.5%
10.1%1
18.5%1
29.3%1
35.4% 44.0%
48.0%1
58.0%1
63.4%1
75.7%
DEAD ENDS (155 X 2 = 310) Target; all dead ends to be flushed twice each year.
FLUSHED THIS MONTH 0
01
01
1551
0 0
01
01
01
1551
1
FLUSHED THIS YEAR 0
01
01
1551
0 155
1551
1551
1551
310
% OF TOTAL 0.0%
0.0%1
0.0%1
50.0%1
50.0% 50.0%
50%
50%
50%1
1
AIR VACS (309) Target; all air /vacs to be serviced annually.
INSPECTED THIS MONTH 0
2051
931
0 1
01
21
11
01
11
1
INSPECTED THIS YEAR 0
2051
2981
298 299
2991
3011
3021
3021
3031
1
% OF TOTAL 0.0%
66.3%1
96.4%1
96.4% 96.8%
96.8%1
97.4%1
97.7%1
97.7%1
98.1%1
1
SEWER CLEANING (802,560) Target; all sewers to be cleaned annually.
CLEANED THIS MONTH 73,825
18,7981
24,9741
104,224 121,202
128,7031
91,8021
130,579
1 93,8431
59,4971
1
CLEANED THIS YEAR 73,825
92,6231
117,5971
221,821 343,023
471,7261
563,5281
694,1071
787,950
1 847,4471
1
% OF TOTAL 9.2%
11.5%1
14.7%1
27.6% 42.7%
58.8%1
70.2%1
86.5%1
98.2%
SEWER TELEVISING (200,640) Target; all sewers to be televised every 4 years.
TELEVISED THIS MONTH 5,334
21,6511
23,1191
5,463
1 809 3,628
7,062
1 2,077
1 13,0221
25,206
TELEVISED THIS YEAR 5,334
26,985
1 50,1041
55,567
1 56,376 60,004
67,0661
69,1431
82,165
1 107,371
% TOTAL 2.7%
13.5%1
25.0%1
27.7%1
28.1% 29.1%
33.4%1
34.5%1
41.0%1
53.5%
ITEM NO. 2.3
AGENDA REPORT
Meeting Date: May 6, 2010
Subject: Monthly Groundwater Producers Meeting Report
ATTACHMENTS:
Name: Dosciiption: a ype:
GWP MtgNotes 14Apr10.pdf Monthly Groundwater Producers Meeting Report Backup Material
Attchmt_to Apr Mtg Notes.pdf BEA Information Backup Material
Yorba Linda
Water District
MEMORANDUM
DATE: April 15, 2010
TO: Ken Vecchiarelli, General Manager
FROM: Steve Conklin, Engineering Manager
COPY: Pat Grady, Assistant General Manager
Lee Cory, Operations Manager
John DeCriscio, Chief Plant Operator
SUBJECT: Groundwater Producers Meeting, April 14, 2010
John DeCriscio and I attended the Groundwater Producers (GWP) Meeting on April 14
at OCWD. Items presented and discussed include the following:
1. Water Quality Update. OCWD staff reported on the Public Health Goal Report,
required to be completed by water providers by July 1, 2010. The State-required
report must be updated every three years, and made available to the public for
review and comment.
2. Status of RA and BPP for FY 2010-11. OCWD staff reported that the proposed
Replenishment Assessment (RA) and Basin Production Percentage (BPP) remain
unchanged at $249/AF and 62%, respectively. The final values will be approved at
the April 21 Board meeting.
3. BEA for FY 2010-11. OCWD staff reported that they plan to recommend to the
OCWD Board on April 21 that the Basin Equity Assessment (BEA) for FY 2010-11
be set at the MWDOC "melded" imported water rate, rather than the MWD Tier 2
water rate. This results in a more equitable water-supply cost for all groundwater
producers, according to OCWD. Further information on this issue is provided on the
attached OCWD Agenda Item Submittal, presented to the OCWD
Administrative/Finance Issues Committee on April 15, 2010.
4. GWR System O&M Agreement with OCSD. OCWD staff reported on the new draft
agreement with OCSD for the above. They noted that the original agreement
included many design and construction items that are no longer relevant. The new
agreement is simpler, relating to ongoing operational items and responsibilities,
whereby each party is responsible for all O&M costs for processes on its property.
5. Buying Additional MWD Untreated Full-Service Water. MWDOC estimates they
will under-utilize their MWD imported-water allocation for FY 09-10. This would
allow OCWD to purchase up to 26,000 acre-feet of MWD full-service untreated water
to recharge the groundwater basin. The total cost of this water is estimated at $14.1
1
million. The OCWD budget for MWD water purchases is $12.6 million. OCWD is
unsure how much of this water can be taken due to recharge system capacity
constraints. If the OCWD Board approves, staff will work to maximize the amount of
water received for recharge, possibly up to 26,000 acre-feet, and exceed the water
budget by $1.5 million.
2
AGENDA ITEM SUBMITTAL
Meeting Date: April 15, 2010 Budgeted: NIA
Budget Amount: NIA
To: Administrative/Finance Issues Cte. Cost Estimate: NIA
Board of Directors Funding Source: NIA
Program/Line Item No.: NIA
From: Mike Markus General Counsel Approval: NIA
Engineers/Feasibility Report: NIA
Staff Contact: J. Kennedy CEQA Compliance: NIA
Subject: DISCUSSION AND REVIEW OF FISCAL YEAR 2010-2011
BASIN EQUITY ASSESSMENT
SUMMARY
Staff plans to recommend on April 21, 2010 using the Municipal Water District of
Orange County (MWDOC) "melded" imported water rate for establishing the fiscal year
(FY) 2010-11 Basin Equity Assessment (BEA). The BEA helps control basin production
and ensures an equitable overall water supply cost for the groundwater producers
(Producers). Since FY2003-04, the District has set the BEA based upon the higher
Metropolitan Water District of Southern California (MWD) Tier IC water rate. Staff will
recommend for FY2010-11 that the District continue using the "Production ,imitation"
and "Surcharge" provisions of the District Act to control groundwater production (These
provisions of the District Act were enacted for the current fiscal year). Therefore, the
BEA will not need to be set based upon the higher MWD Tier II water rate.
RECOMMENDATION
Informational
DISCUSSION/ANALYSIS
Background Information
The Basin Production Percentage (BPP) and the Basin Equity Assessment (BEA) were
established and incorporated into the District Act in 1969. The BPP and BEA help
control basin pumping and ensure that the Producers generally have the same overall
water supply cost. With the BPP and BEA, there is no cost advantage to a Producer
who may chose to pump above the BPP, because the cost of groundwater pumped
above the BPP is charged the BEA (in addition to the Replenishment Assessment (RA)
and pumping energy cost), which brings the cost of that groundwater up to imported
water costs. By maintaining water supply cost equity for all of the Producers, no agency
1
can be disadvantaged. This is an important goal in managing a non-adjudicated
groundwater basin.
The BEA is established based upon the MWD Tier 11 water supply cost which is
currently $8051af after including applicable readiness-to-serve ($30faf) and capacity
($151af) charges along with the MWDOC increment ($6.501af) charge. The BEA is
equal to the difference between this MWD rate and the combined total of the RA and
each Producer's energy cost to pump groundwater (as shown on Figure 1). The
average BEA is $4961af for FY2009-10.
Figure 1
FY09-10 Basin Equity Assessment Calculation
$1,000
$900 $8051af
$800 I $677faf
$700 I 13 Basin Equity
$600 $496 Assessment
$500 (current $368
619- $400 SEA) (potential ❑ Producers
BEA)
Average Well
$300
$200 Energy Cost
$100 $249 $249 El Replenishment
Assessment
$0
MWD Tier II Rate MWDOC Melded
Rate
The Producers, who are MWDOC member agencies, pay a melded rate (weighted
average of MWD Tier I and Tier II water supply cost) to MWDOC for imported water as
shown below (as shown in Figure 2). MWDOC mostly pays the Tier I rate to MWD but
can purchase small amounts of Tier II water depending upon total area water demands
and the BPP.
Figure 2
MWDOC Melded Rate
MIND
Tier II Rate paid
By MWDQC MWDOC
MWDOC MWDOC 10 Member
Melded Rate Aaencies
MWD
Tier I Rate paid
By MWDOC
2
Prior to FY2003-04, the BEA was established based upon the actual cost Producers
paid for MWD water, which is currently the MWDOC melded rate. However, since
FY2003-04, the BEA has been based on the higher MWD Tier II water supply cost. This
creates a minor financial penalty for Producers who pump above the BPP. Figure 1 also
demonstrates how the FY09-10 BEA would be lower if it was established based on the
MWDOC melded rate.
Issues
Setting the BEA based upon the higher MWD Tier II rate has created issues which are
described below.
The BEA, by definition, is an "equity assessment" for those Producers who
chose to pump above the BPP and was originally intended to be based upon
the marginal cost of purchasing additional imported water supplies which is
currently the MWDOC melded rate. As previously discussed, the BEA was
originally established to equate the overall water supply cost of a Producer
who pumps above the BPP with a Producer who does not. By setting the
BEA based upon the higher MWD Tier II rate, the Producer pumping above
the BPP now has a higher water supply cost than a Producer who does not.
This is not a significant basin management issue but is a minor inconsistency
with the original intent of the charge.
♦ Producers who construct and operate groundwater remediation projects and
participate in the BEA exemption program are being financially penalized with
the higher BEA. This directly conflicts with the District's desire to provide a
financial incentive for Producers to implement these types of projects. The
accounting for this program is complex; however by using a higher BEA, the
Producers project capital costs are not fully repaid. The Producer begins
making BEA payments to the District faster than would be expected resulting
in a loss to the Producer.
♦ The District has implemented programs to transfer groundwater production
from the coast to inland areas such as the Coastal Pumping Transfer
Program. A program was recently administered with Mesa Consolidated
Water District and the City of Orange in FY2008-09. These types of
programs are more complicated to administer when the BEA is not
established based upon the Producer's actual cost of imported water supply
which is the MWDOC melded rate.
a Producers can sometimes inadvertently slightly exceed the BPP and pay the
higher BEA or pump too far below the BPP to avoid the BEA payment. In
June of each year the Producers are closely monitoring their systems and the
amount of groundwater they produce to ensure they pump up to the BPP but
not go over. Balancing total water demands with imported water purchases
3
and groundwater production can be difficult. By slightly going over the BPP,
and with the BEA set based upon MWD Tier II rates, the Producers are
paying slightly more for their water supply. This leads Producers to pump too
much under the BPP for fear of paying the higher BEA and leaving
groundwater "on the table". Having the BEA based upon the MWDQC
melded rate would provide a friendlier system to the Producers.
Production Limitation and Surcharge
As shown in Figure 3 below, in FY2009-10 the District established a 62% BPP and a
64% "Production Limitation" as allowed in the OCWD Act. Pumping above the 62%
BPP would pay the BEA. Pumping above the 64% "Production Limitation" would pay
the BEA and a "Surcharge" as also allowed in the OCWD Act. The "Surcharge" amount
could vary annually but would need to be set to create a financial disincentive for
pumping above the Production Limitation amount. Because MWD is currently
allocating imported water supplies and charging large penalties for agencies exceeding
their allocation, the surcharge amount was set high at $2,400 per acre-foot (faf). This
amount is based upon the highest potential MWDIMWDOC allocation penalty rate.
Figure 3
FY2009-10 BPP, BEA and Production Limitation
E go%
$0%
o 0 Pay RA, $496faf BEA and
21 7"~/~ c~ siF~r~71 a ion $2,400/af sucharge
60% i 6~BPP .
50%M Pay RA and $4961af BEA
40°h
L
30% -
0 20,%- 0 Pay IAA
ci 10%
a
0%
With the BEA and "Surcharge" amount, and how MWD and MWDOC are administering
the potential allocation penalties, pumping above the 64% "Production Limitation" would
be more expensive than paying the allocation formula penalty rates. Thus an economic
incentive would exist to not pump above the 64% amount.
4
Staff recommends that the District again provide this option to the Producers in
FY2010-11 to provide them the option to pump a small amount of additional
groundwater (between 62% and 64%) if they are facing the MWD/MWDOC allocation
penalty rates to take advantage of groundwater basin supplies.
The amount of additional basin pumping that may occur is unknown but is not expected
to be significant. At most approximately an additional 9,000 of of groundwater pumping
would occur. The District would receive additional revenues of up to approximately
$6.5 million if an additional 9,000 of of pumping did occur.
Three Cities
The cities of Anaheim, Fullerton and Santa Ana are MWD member agencies and pay
Tier I and Tier II water rates to MWD. When pumping above the BPP, the three cities
can avoid MWD Tier 11 charges depending upon their total water demands and where
the BPP is set. Thus, it could be appropriate to continue establishing the BEA for the
three cities at the MWD Tier II rate at this time.
However, the District will need to work closely with the three cities annually to adjust
their BEA so that it is based upon their actual avoided cost of pumping above the BPP.
If the BPP were to increase and/or if their total water demands decrease sufficiently, the
BEA for any or all of the three cities may need to be based upon the MWD Tier I rate.
The City of Fullerton has indicated this is the case for their system.
PRIOR RELEVANT BOARD ACTION(S) N/A
5
ITEM NO. 2.4
AGENDA REPORT
Meeting Date: May 6, 2010
Subject: Status Report on Capital Projects in Progress
ATTACHMENTS:
Name: Dosciiption: a ype:
CIP Rept May10.pdf Status Report on Capital Projects in Progress Backup Material
CAPITAL IMPROVEMENT PROJECTS STATUS REPORT
Date: May 1, 2010
New Information since Last Report is Shown in Red
IN CONSTRUCTION
Project
Current Status
Next Actions
Comments
1
Highland Reservoir
Second and third roof pours are
Placing rebar and cleaning
On schedule with no significant
Budget: $11,200,000 Job No. 200309
completed.
forms for final roof pour.
issues outstanding.
Project Contact: Joe Polimino
Planned Completion Date: August 2010
2
Hidden Hills Res & Santiago BPS
Shoring removed; all internal
Pressure test pipeline storm
Received draft easement documents
Budget: $7,000,000 Job No.200028
finishing complete. Stairs are
drain. Finish roof pour for
from State Parks for construction of
Project Contact: Joe Polimino
installed and final painting is
inlet vault and hatches on roof,
paved access road to reservoir. Draft
Planned Completion Date: July 2010
being applied to piping in
Finish vents and other roof
documents were also completed and
reservoir. Storm drain and pipe
items. Santiago controls
provided to SCE.
complete to reservoir.
almost completed.
3
Photovoltaic Panels —Admin Bldg
Solar System connected to
Complete final wiring of
Training and final punch list to be
Budget: $250,000 Job No. 200912
Edison power grid and locked
inverters and call for final City
prepared for project completion.
Project Contact: Hank Samaripa
out until final inspection. All
of Placentia inspection. After
Akeena Solar to process $72,000
Planned Completion Date: May 2009
solar panels installed on roof.
final, contact SCE for
CSI rebate request for the District.
commissioning.
4
Wells 1, 5 and 12 Upgrade
Analyzing W -12 refurbishment.
Finalize W -12 replacement
W -5 in operation.
Budget: $190,000 Job No. 200813
W -5 pump installation
specifications. .
Project Contact: Anthony Manzano
complete, start-up testing
Project Completion: TBD
successful, passed bacti test.
5
Well 20
Contractor completing well
Well development expected to
Plan to receive draft Preliminary
Budget: $2,000,000 Job No.200711
drilling. Wellhead Equipping
be completed by week of May
Design Report for wellhead
Project Contact: Anthony Manzano
design started by Civiltec
3rd.
equipping June 2010.
Planned Completion Date: TBD
Engineering Inc.
IN DESIGN
Project
Current Status
Next Actions
Comments
1
OC -51 Connection Upgrade
District provided response to
Meet with MWDOC staff to
Coordinate w/ MWDOC staff to
Budget: $242,000 Job No. 200815
MWD through MWDOC
discuss further plans upon
address additional concerns MWD
Project Contact: Derek Nguyen
regarding comments received
receipt of MWD's 2nd
might bring forth.
Planned Completion Date: TBD
in MWD letter. Awaiting
response.
response from MWD.
2
Highland Booster Station Upgrade
District review of 90% design
Prepare Invitation -to -Bid
Review SCE and Gas Co. rebate
Budget: $6,000,000 Job No. 200814
plans and specs completed.
documents and decide on
opportunities for the Highland BPS
Project Contact: Hank Samaripa
MWH to revise documents and
advertisement date and final
Replacement Project.
Planned Completion Date: Mid 2011
issue 100% plans and specs.
bid date.
3
Anaheim Intertie Connection
Review 100% plans and
Set up pre - proposal meeting
Evaluate bids and select General
Budget: $250,000 (YLWD Share)
specifications completed and
with five contractors. Walk the
Contractor. Coordinate with
Job No. 200906
sent to Steve Andrews
three inter -tie locations. Allow
Anaheim Public Works.
Project Contact: Hank Samaripa
Engineering. Prepared a short-
three weeks to bid.
Planned Completion Date: July 2010
list of General Contractors for
construction phase.
4
Ohio St Pipeline Replacement Project
Reviewed and approved Tetra
Complete Professional
Will bring PSA to Board for
Budget: $530,000 Job No. 201005
Tech's proposed work scope
Services Agreement and
ratification.
Project Contact: Anthony Manzano
and fee for engineering
schedule design kick -off
Planned Completion Date: TBD
services.
meeting.
5
Vista del Verde Valve Replacement
Pre - ordered valves received.
Pre -bid meeting with short-list
Work planned for late June or early
Budget: $1M Job No. 200908
Bid documents prepared for
of contractors. Receive bids
July.
Project Contact: Derek Nguyen
Phase 1 work.
and award contract for first-
Planned Compl. Date: July 2010 (Ph. 1)
phase of work.
IN PLANNING
Project
Current Status
Next Actions
Comments
1
Fairmont Site Improvements
Agreement approved by
S &S has proposed a code
Present schedule to Operations and
Budget: $300,000 (YLWD share)
Board. Waiting for signed
update review by City.
Production departments.
Job No. 200803
agreement from S &S. S &S
Contact S &S for preliminary
Project Contact: Hank Samaripa
has delayed signing pending
kickoff meeting to establish
Planned Completion Date: TBD
completion of other priorities.
schedule.
2
Recycled Water Study
Gathering data on large
Provide updated irrigation
Coordinate and begin work with
Budget: $1,800,000 Job No. 200807
landscape users and compiling
demand data and projected
Consultant on project tasks.
Project Contact: Derek Nguyen
demand data for Consultant.
customers to Malcolm Pirnie &
Planned Completion Date: TBD
sewer -flow monitoring data
3
West Wellfield Project
Investigating additional
Review hydrogeology data and
May retain a Property Acquisition
Budget: $9,000,000 Job No.
potential well sites east of
contact land owners to
Firm for assistance.
Project Contact: Anthony Manzano
Tustin Avenue
determine if there is interest in
Planned Completion Date: TBD
selling small site for well.
4
Asset Management Plan (AMP)
Carollo to conduct training
Prepare priority listing of high
Follow up with GIS on correcting
Budget: $120,000 Job No. 200909
module for the AMP project
risk items, review each and
discrepancies on the District water
Project Contact: Hank Samaripa
on May10, 2010.
prepare cost estimate for future
and sewer Atlas Maps.
Planned Completion Date: Feb. 2010
budgets.
5
Sewer Master Plan (SMPU)
Flow monitoring complete.
Consultant to refine GIS base,
Modeling expected to start later this
Budget: $350,000 Job No. 200916
Sewer system GIS database
finalize flow monitoring
month.
Project Contact: Anthony Manzano
completed by staff & being
results, and start model.
Planned Completion Date: August 2010
finalized by Consultant.
6
Lakeview Grade Separation
Preliminary pipeline relocation
60% design submittal due late
Awaiting OCTA decision to
Budget: TBD Job No. 201002
alignment finalized.
May 2010 for YLWD review.
determine agency financially
Project Contact: Anthony Manzano
responsible for pipe relocation.
Planned Completion Date: Sept. 2013
7
Palm Ave. Booster Station
Scheduled kick -off meeting
Meet with City to discuss siting
Prepare Preliminary project cost and
Budget: TBD Job No. 200817
with Operations to review
in Jessamyn West Park and
schedule. Prepare RFP for
Project Contact: Hank Samaripa
objectives of project and
other issues and concerns for
environmental and engineering
Planned Completion Date: July 2011
options.
new booster station.
services.
ITEM NO. 2.5
AGENDA REPORT
Meeting Date: May 6, 2010
Subject: Second Version of Capital Improvement and Replacement Projects Budget
ATTACHMENTS:
Name: cv, i~a$icri: a ype:
3 YR CIP 2010-13.pdf 3 Yr CIP 2010-13 Backup Material
Projects in Progress from Board-Approved 2007-12 CIP Change
Projects Budgeted 09-10 Total Cost 09-10 FY 2010-11 FY 2011-12 FY 2012-13 Total Over or (Under) Budget
Improvement Projects
Highland Reservoir $ 3,952,000 $ 4,360,000 $ 240,000 $ 4,600,000 $ (576,000)
New Well 20 $ 590,000 $ 518,500 $ 1,025,000 $ 1,543,500 $ (71,500)
Wells 1,5,12 Upgrade $ 190,000 $ 200,000 $ 150,000 $ 350,000 $ 160,000
OC-51 Upgrade $ 100,000 $ 95,000 $ 75,000 $ 170,000 $ 70,000
Fairmont BPS Pump Retrofit $ - $ 400,000 $ 400,000 $ -
Zone Reconfig. Pipelines $ 1,300,000 $ 1,024,500 Completed $ 1,024,500 $ (275,500)
San Antonio PRS Upgrades $ 270,000 $ 262,900 Completed $ 262,900 $ (7,100)
Hidden Hills Reservoir $ 5,500,000 $ 5,342,000 $ 158,000 $ 5,500,000 $ -
Anaheim Interties $ 150,000 $ 75,100 $ 46,000 $ 121,100 $ (28,900)
Lakeview Fencing&Landscaping $ 210,000 $ 77,000 $ 50,000 $ 127,000 $ (83,000)
GIS Implementation $ 100,000 $ 11,900 $ 60,000 $ 71,900 $ (28,100)
Fairmont Site Improvements $ 300,000 $ - $ 300,000 $ 300,000
Fire Flow Impvmts Via Sereno & Ohio $ 25,000 $ 25,000 $ 100,000 $ 125,000
Foxtail Pipeline $ 50,000 $ - $ 245,000 $ 245,000
Elk Mtn. Reservoir Site Impvmts. $ - $ 300,000 $ 300,000
Palm Ave BPS Replacement $ 540,000 $ - $ 500,000 $ 3,900,000 $ 1,000,000 $ 5,400,000
Zone 5 BPS $ 270,000 $ - $ 540,000 $ 540,000 $ 1,080,000
Replacement Projects
Lakeview Sewer Lift Sta Upgrade $ 220,000 $ 202,000 Completed $ 202,000 $ (18,000)
2007-12 Program SUBTOTAL $ 13,767,000 $ 12,193,900 $ 3,894,000 $ 4,735,000 $ 1,000,000 $ 21,822,900 $ (858,100)
New Project for CIP/CRP
Improvement Projects
Asset Management Plan $ 120,000 $ 124,100 Completed $ 124,100 $ 4,100
Sewer Master Plan $ 350,000 $ 150,000 $ 200,000 $ 350,000
GIS/CMMS $ 200,000 $ 300,000 $ 300,000
Zone Interconnect Stub-ups(3) $ 120,000 $ 120,000 $ 120,000
Highland BPS Upgrade $ 1,000,000 $ 598,300 $ 5,500,000 $ 6,098,300 $ (1,401,700)
Mixing/Re-Chlor Facil at 2 Res Sites $ 76,800 $ 80,000 $ 156,800 $ 56,800
Non-Pot Water Facil for Irrig Use $ 50,000 $ 225,000 $ 525,000 $ 1,000,000 $ 1,800,000
West Wellfield $ 500,000 $ 40,000 $ 1,060,000 $ 4,000,000 $ 4,000,000 $ 9,100,000 $ 100,000
Fire Flow Pipeline Improvements $ 300,000 $ 300,000
Admin Bldg Solar Power System $ 218,100 $ (73,000) $ 145,100 $ 145,100
Replacement Projects
Vista del Verde Valve Replacement $ 500,000 $ 104,200 $ 600,000 $ 704,200 $ (295,800)
Valley View Pipeline Replacement $ 120,000 $ - $ 120,000 $ 120,000
Blair Drive Pipeline Replacement $ 50,000 $ - $ 50,000 $ 50,000
Highland Pipeline Replacement $ 120,000 $ - $ 120,000 $ 120,000
Plumosa Water Line Relining $ 110,000 $ - $ 110,000 $ 110,000
Bastanchury Pipeline Replacement $ 1,300,000 $ - $ 1,300,000 $ 1,300,000
Ohio St. Pipeline Replacement $ 60,000 $ 470,000 $ 530,000
Fairmont Reservoir Repairs $ 205,000 $ 205,000
Pebble Beach Rd Pipeline Replacement $ 150,000 $ 150,000
Wabash & Short St Pipeline Impvmts. $ 132,000 $ 132,000
South Grandview St Improvements $ 100,000 $ 100,000
Hidden Hills Pipeline Replacement $ 90,000 $ 90,000
Richfield Rd Pipeline Liner $ 200,000 $ 200,000
Oriente Dr. Pipeline Replacement $ 304,000 $ 304,000
Imperial Hwy. Pipeline Replacement $ 340,000 $ 340,000
Proposed New Projects SUBTOTAL $ 4,490,000 $ 1,421,500 $ 9,511,000 $ 5,377,000 $ 6,940,000 $ 22,649,500 $ (1,391,500)
COMBINEDTOTAL $ 18,257,000 $ 13,615,400 $ 13,405,000 $ 10,112,000 $ 7,940,000 $ 44,472,400 $ (2,249,600)
Color Key:
Approved by Board for 2009-10 Budget
Approved by Board October 15, 2009
Approved "Urgent" Project April 2010
Proposed Additional Projects for 2010-11 Budget
Projects in Progress from Board-Approved 2007-12 CIP Change
Projects Budgeted 09-10 Total Cost 09-10 FY 2010-11 FY 2011-12 FY 2012-13 Total Over or (Under) Budget
Improvement Projects
Highland Reservoir $ 3,952,000 $ 4,360,000 $ 240,000 $ 4,600,000 $ (576,000)
New Well 20 $ 590,000 $ 518,500 $ 1,025,000 $ 1,543,500 $ (71,500)
Wells 1,5,12 Upgrade $ 190,000 $ 200,000 $ 150,000 $ 350,000 $ 160,000
OC-51 Upgrade $ 100,000 $ 95,000 $ 75,000 $ 170,000 $ 70,000
Fairmont BPS Pump Retrofit $ - $ 400,000 $ 400,000 $ -
Zone Reconfig. Pipelines $ 1,300,000 $ 1,024,500 Completed $ 1,024,500 $ (275,500)
San Antonio PRS Upgrades $ 270,000 $ 262,900 Completed $ 262,900 $ (7,100)
Hidden Hills Reservoir $ 5,500,000 $ 5,342,000 $ 158,000 $ 5,500,000 $ -
Anaheim Interties $ 150,000 $ 75,100 $ 46,000 $ 121,100 $ (28,900)
Lakeview Fencing & Landscaping $ 210,000 $ 77,000 $ 50,000 $ 127,000 $ (83,000)
CIS Implementation $ 100,000 $ 11,900 $ 60,000 $ 71,900 $ (28,100)
Fairmont Site Improvements $ 300,000 $ - $ 300,000 $ 300,000
Fire Flow Impvmts Via Serene & Ohio $ 25,000 $ 25,000 $ 100,000 $ 125,000
Foxtail Pipeline $ 50,000 $ - $ 245,000 $ 245,000
Elk Mtn. Reservoir Site Impvmts. $ - $ 300,000 $ 300,000
Palm Ave BPS Replacement $ 540,000 $ - $ 500,000 $ 3,900,000 $ 1,000,000 $ 5,400,000
Zone 5 BPS $ 270,000 $ - $ 540,000 $ 540,000 $ 1,080,000
Replacement Projects
Lakeview Sewer Lift Sta Upgrade $ 220,000 $ 202,000 Completed $ 202,000 $ (18,000)
2007-12 Program SUBTOTAL $ 13,767,000 $ 12,193,900 $ 3,894,000 $ 4,735,000 $ 1,000,000 $ 21,822,900 $ (858,100)
New Project for CIP/CRP
Improvement Projects
Asset Management Plan $ 120,000 $ 124,100 Completed $ 124,100 $ 4,100
Sewer Master Plan $ 350,000 $ 150,000 $ 200,000 $ 350,000
GIS/CMMS $ 200,000 $ 300,000 $ 300,000
Zone Interconnect Stub-ups (3) $ 120,000 $ 120,000 $ 120,000
Highland BPS Upgrade $ 1,000,000 $ 598,300 $ 5,500,000 $ 6,098,300 $ (1,401,700)
Mixing/Re-Chlor Facil at 2 Res Sites $ 76,800 $ 80,000 $ 156,800 $ 56,800
Non-Pot Water Facil for Irrig Use $ 50,000 $ 225,000 $ 525,000 $ 1,000,000 $ 1,800,000
West Wellfield $ 500,000 $ 40,000 $ 1,060,000 $ 4,000,000 $ 4,000,000 $ 9,100,000 $ 100,000
Fire Flow Pipeline Improvements $ 300,000 $ 300,000 $ 600,000 $ 600,000
Admin Bldg Solar Power System $ 218,100 $ (73,000) $ 145,100 $ 145,100
Replacement Projects
Vista del Verde Valve Replacement $ 500,000 $ 104,200 $ 600,000 $ 704,200 $ (295,800)
Valley View Pipeline Replacement $ 120,000 $ - $ 120,000 $ 120,000
Blair Drive Pipeline Replacement $ 50,000 $ - $ 50,000 $ 50,000
Highland Pipeline Replacement $ 120,000 $ - $ 120,000 $ 120,000
Plumosa Water Line Relining $ 110,000 $ - $ 110,000 $ 110,000
Bastanchury Pipeline Replacement $ 1,300,000 $ - $ 1,300,000 $ 1,300,000
Ohio St. Pipeline Replacement $ 60,000 $ 470,000 $ 530,000
Fairmont Reservoir Repairs $ 205,000 $ 205,000
Pebble Beach Rd Pipeline Replacement $ 150,000 $ 150,000
Wabash &Short St Pipeline Impvmts. $ 132,000 $ 132,000
South Grandview St Improvements $ 100,000 $ 100,000
Hidden Hills Pipeline Replacement $ 90,000 $ 90,000
Richfield Rd Pipeline Liner $ 200,000 $ 200,000
Oriente Dr. Pipeline Replacement $ 304,000 $ 304,000
Imperial Hwy. Pipeline Replacement $ 340,000 $ 340,000
Proposed New Projects SUBTOTAL $ 4,490,000 $ 1,421,500 $ 9,511,000 $ 5,377,000 $ 6,940,000 $ 23,249,500 $ (791,500)
COMBINED TOTAL $ 18,257,000 $ 13,615,400 $ 13,405,000 $ 10,112,000 $ 7,940,000 $ 45,072,400 $ (1,649,600)
Color Key:
Approved by Board for 2009-10 Budget Revised: 6-May-10
Approved by Board October 15, 2009
Approved "Urgent" Project April 2010
Proposed Additional Projects for 2010-11 Budget