HomeMy WebLinkAbout2010-09-08 - Planning-Engineering-Operations Committee Meeting Minutes
MINUTES OF THE
YORBA LINDA WATER DISTRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
September 8, 2010
A meeting of the Planning-Engineering-Operations Committee was called to order by
Director Mills at 4:00 p.m. The meeting was held at the District's Administrative Office
at 1717 E Miraloma Ave, Placentia CA 92870.
COMMITTEE STAFF
Director William R. Mills, Chair Ken Vecchiarelli, General Manager
Director John Summerfield Lee Cory, Operations Manager
Anthony Manzano, Sr. Project Manager
John DeCriscio, Chief Plant Operator
1. PUBLIC COMMENTS
None.
2. DISCUSSION ITEMS
2.1. Monthly Groundwater Production and Purchased Import Water Report
Mr. DeCriscio reported that water demand for August was 4.0% under the
budget projection and reported that the conservation percentage since
July 1, 2009 is still at 18.0% overall. Mr. DeCriscio also showed a graph
for August 2010 water supply and reported that 34.8% of demands were
met with groundwater, which is close to staff's operational goal of 35% for
the summer months and 65.2% import water was supplied to meet the
monthly demands. Mr. DeCriscio also noted that the temperature for the
month of August was slightly cooler than in 2008 and 2009.
2.2. Monthly Preventative Maintenance Program Report
Mr. Cory reported that the PM is continuing pretty much on schedule.
The Committee inquired about some of the items that were below
projections and Mr. Cory responded to their questions. Director Mills and
Summerfield also inquired about the sewer TV equipment and Mr. Cory
mentioned that the District did receive the back-up crawler equipment so
that item should pick up in pace over the next few months.
2.3 Report on Brush Fire in Yorba Linda Hills Saturday, September 4, 2010
(The Committee agreed to add Item 2.3 for discussion as the incident
occurred after the agenda was posted.)
Mr. DeCriscio reported that staff's response to the fire Saturday night was
prompt and reservoirs in the area of the fire were in the process of being
filled to capacity as soon as staff received word of the incident. The fire
was put-out quickly by OCFA and other fire crews. No water shortages or
pressure issues were reported.
1
3. ACTION CALENDAR
3.1. Approval of Change Order No. 3, Final Progress Payment Number 15 and
the Notice of Completion for the Hidden Hills Reservoir Project
Mr. Vecchiarelli reported that this item represents the final change order
and translates to a negative change order overall for the project. Director
Mills asked if this was the same contractor (Pacific Hydrotech Corporation
- PCH) that was recently awarded the Highland Booster Pump Station
Project and Mr. Vecchiarelli confirmed that it is. Mr. Vecchiarelli stated
that this item is scheduled for consideration on the Consent Calendar for
tomorrow's Board meeting. Following discussion, the Committee
supported staff's recommendation for approval of Change Order No. 3 in
the amount of $3,002.27 and one additional calendar day, Final Progress
Payment No. 15 in the amount of $418,817.04, and authorization to file
the Notice of Completion.
3.2. Geotechnical Services for the Highland Booster Station Replacement
Project
Mr. Vecchiarelli reported that these services are for the Highland Booster
Station. Mr. Manzano reported that Ninyo and Moore was a very qualified
firm and that their Principal has nearly 35 years experience and that their
staff is also well qualified. Following discussion, the Committee supported
staff's recommendation to execute a Professional Services Agreement
with Ninyo & Moore, for a fee not to exceed $30,494.
3.3. Water Supply Assessment for the City of Yorba Linda 2008-2014 Housing
Element
Mr. Vecchiarelli reported that the Water Supply Assessment (WSA) was
being completed as a requirement because the Project exceeds 500
dwelling units. Director Summerfield inquired about how projects like this
may affect our conservation measures since an increase in development
would increase demands. Mr. Vecchiarelli mentioned that OCWD
manages the groundwater basin and MWDOC manages the water
allocations from MWD. While both of these resources are currently
experiencing restrictions, the current allocation levels and long term water
supply status factors in future development and growth in demands. Even
with the mandate to achieve 20% reduction by 2020, continued
development is still included in the total water supply available into the
future. Mr. Vecchiarelli mentioned that the WSA was modified and Mr.
Manzano handed-out the revised copies of the draft WSA to the
Committee members and both Mr. Vecchiarelli and Manzano briefly
discussed the minor changes. Director Mills asked if this would be on the
Board Agenda and Mr. Vecchiarelli stated that this will go to the Board
Meeting for consideration on September 23. Following discussion, the
Committee supported staff's recommendation that the Board adopt the
WSA at its September 23 meeting, for incorporation into the City's Project
Draft EIR.
2
3.4. Well No. 20 Engineering Services Amendment No. 1 with Civiltec
Engineering, Inc.
Mr. Vecchiarelli reported that this change order request is primarily a
result of keeping Well 11 for back-up until the well is no longer useful.
Director Mills asked if there is sand produced from this or other wells and
Mr. Vecchiarelli reported that sand production has been minimal. Mr. Cory
added that some customers in the food services industry and circuit board
manufacturing are sensitive to this and that it is very limited in our system.
Following discussion, the Committee supported staff's recommendation to
authorize Engineering Services amendment No. 1 with Civiltec
Engineering Inc. for a fee increase not to exceed $9,500.
4. DISCUSSION ITEMS
4.1. Monthly Groundwater Producers Meeting Report
Mr. Vecchiarelli reported that he attended this meeting with Mr. Conklin
and that this was the first major meeting for the Annexation Workshop with
no major decisions being made. OCWD is expecting to receive four
proposals to complete the draft EIR for annexations. Mr. Vecchiarelli also
reported that IRWD may also reconsidering locating production wells
within the City of Anaheim with YLWD at the proposed West Wellfield
location. They may instead utilize available production capacity in their
Dyer Road Wellfield.
4.2. Status Report on Capital Projects in Progress
Mr. Vecchiarelli asked the Committee members if they had any questions
about the CIP Status Report and Director Mills asked about the status of
the Recycled Water Study. Mr. Vecchiarelli stated that the draft report is
expected by the end of the month. Director Mills also asked about the
2010 Waterline Replacement Project and Mr. Vecchiarelli reported that
this project includes pipelines that need to be replaced as identified in the
Asset Management Plan and other reports.
4.3. Future Agenda Items and Staff Tasks.
Staff will research and report on the City's conservation over the past 14
months and bring this report back to the Committee at their meeting next
month.
5. ADJOURNMENT
5.1. The meeting adjourned at 5:00 p.m. The next regular meeting of the
Planning-Engineering-Operations Committee, originally scheduled for
October 7, 2010, was rescheduled to Wednesday, October 6, 2010 at 4:00
PM.
3