AGENDA
YORBA LINDA WATER DISTRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
Thursday, February 3, 2011, 4:00 PM
1717 E Miraloma Ave, Placentia CA 92870
COMMITTEE STAFF
Director Gary T. Melton, Chair Ken Vecchiarelli, General Manager
Director Ric Collett Steve Conklin, Engineering Manager
Lee Cory, Operations Manager
John DeCriscio, Chief Plant Operator
Derek Nguyen, Water Quality Engineer
1. PUBLIC COMMENTS
Any individual wishing to address the committee is requested to identify themselves and state the matter on
which they wish to comment. If the matter is on this agenda, the committee Chair will recognize the individual for
their comment when the item is considered. No action will be taken on matters not listed on this agenda.
Comments are limited to matters of public interest and matters within the jurisdiction of the Water District.
Comments are limited to five minutes.
2. DISCUSSION ITEMS
This portion of the agenda is for matters such as technical presentations, drafts of proposed policies, or similar
items for which staff is seeking the advice and counsel of the Committee members. This portion of the agenda
may also include items for information only.
2.1. Water Quality Discussion - Hard Water, Taste & Odor Concerns
2.2. Monthly Groundwater Production and Purchased Import Water Report (To be provided
at the meeting.)
2.3. 2011 MWD Shutdown
2.4. Monthly Preventative Maintenance Program Report (To be provided at the meeting.)
2.5. Status Report on Capital Projects in Progress
2.6. Groundwater Producers Meeting Report
3. ACTION CALENDAR
This portion of the agenda is for items where staff presentations and committee discussions are needed prior to
formal committee action.
3.1. Amendment No. 3 to MWH Americas Professional Services Agreement - Construction
Support Services for the Highland Booster Pump Station Replacement
Recommendation: That the Committee recommend the Board of Directors approve
Amendment No. 3 to the Professional Services Agreement (PSA) with MWH
Americas, in the amount of $219,79 1, for additional construction support services
for the Highland Booster Pump Station Replacement and Expansion Project, Job
No. 200814.
4. DISCUSSION ITEMS CONTINUED
4.1. Future Agenda Items and Staff Tasks
5. ADJOURNMENT
5.1. The next regular meeting of the Planning-Engineering-Operations Committee will be held
March 3, 2011 at 4:00 p.m.
Items Distributed to the Committee Less Than 72 Hours Prior to the Meeting
Pursuant to Government Code section 54957.5, non-exempt public records that relate to open session agenda items
and are distributed to a majority of the Committee less than seventy-two (72) hours prior to the meeting will be available
for public inspection in the lobby of the District's business office located at 1717 E. Miraloma Avenue, Placentia, CA
92870, during regular business hours. When practical, these public records will also be made available on the District's
internet website accessible at http://www.ylwd.com/.
Accommodations for the Disabled
Any person may make a request for a disability-related modification or accommodation needed for that person to be
able to participate in the public meeting by telephoning the Executive Secretary at 714-701-3020, or writing to Yorba
Linda Water District, P.O. Box 309, Yorba Linda, CA 92885-0309. Requests must specify the nature of the disability and
the type of accommodation requested. A telephone number or other contact information should be included so the
District staff may discuss appropriate arrangements. Persons requesting a disability-related accommodation should
make the request with adequate time before the meeting for the District to provide the requested accommodation.
ITEM NO. 2.1
AGENDA REPORT
Meeting Date: February 3, 2011 Budgeted: N/A
Total Budget: N/A
To: Planning-Engineering- Cost Estimate: N/A
Operations Committee
Funding Source: N/A
From: Ken Vecchiarelli, General Account No: N/A
Manager
Job No: N/A
Presented By: Steve Conklin, Engineering Dept: Engineering
Manager
Reviewed by Legal: N/A
Prepared By: Derek Nguyen, Water Quality CEQA Compliance: N/A
Engineer
Subject: Water Quality Discussion - Hard Water, Taste & Odor Concerns
SUMMARY:
Taste and odor concerns along with water hardness are topics often raised by District customers.
Staff will present a verbal report on these issues and provide an update on recent changes in
system operations.
DISCUSSION:
Dealing with taste and odor resulting from the mixture of imported water and groundwater has
always been a challenge for the District. Typically, the District supplies half of its service area with
groundwater and the other half with imported water. However, because of the variability in supply
and demand, certain portions of the District are sometimes served with a mixture of both water
supplies. The disinfection process for each water source is different. Groundwater is disinfected
with free chlorine and imported water is disinfected with chloramine (a combination of chlorine and
ammonia). The mixing of the two can sometimes result in taste and odor complaints from District
customers.
Hard water is also a source of customer complaints, especially those being served primarily with
groundwater. Because of the nature of the aquifer, where water is stored between layers of rock
and sand, minerals such as calcium and magnesium get dissolved into the water and pumped out
of the ground. Much of the District's groundwater contains fairly high hardness levels. While
minerals are beneficial for drinking, high water hardness can lead to mineral deposits on glassware
and dishes, a source of complaints from customers.
Staff will present a verbal report on the topics of water hardness and taste and odor to the PEO
Committee.
ITEM NO. 2.2
AGENDA REPORT
Meeting Date: February 3, 2011
Subject: Monthly Groundwater Production and Purchased Import Water Report (To be
provided at the meeting.)
ATTACHMENTS:
Narn9: Doscrip ion: u
GW Production and Purchased Water Report.pdf Monthly Report Backup Material
YLWD SOURCE WATER SUMMARY
FY 2010-2011
TOTAL MONTHLY YTD BUDGET
GW IMPORT DEMAND GW GW (Demand Est.) DELTA
MONTH (AF) (AF) (AF) (AF)
Jul-10 793.2 1,476.0 2,269.2 35.0% 35.0% 2,483.5 -8.6%
Aug-10 817.3 1,529.5 2,346.7 34.8% 34.9% 2,443.4 -4.0%
Sep-10 753.6 1,404.8 2,158.4 34.9% 34.9% 2,143.8 0.7%
Oct-10 449.1 936.4 1,385.5 32.4% 34.5% 1,808.3 -23.4%
Nov-10 427.8 917.5 1,345.2 31.8% 34.1% 1,428.5 -5.8%
Dec-10 226.2 694.7 920.8 24.6% 33.3% 1,285.0 -28.3%
Jan-11 873.5 281.1 1,154.6 75.7% 37.5% 1,120.4 .0"r
Feb-11 1,071.9
Mar-11 1,270.2
Apr-11 1,588.8
May-11 2,101.6
Jun-11 2, 354.8
FYTD 4,340.6 7,240.0 11,580.6 37.5% 12,712.8 -8.9%
Allowable GW (YTD) 5,313.2 (AF)
Underpumped 972.6 (AF)
Conservation Percentage
Since July 1, 2009 -19.4%
GROUNDWATER PERCENTAGE
80.0%
70.0%
60.0%
50.0%
40.0%
MONTHLY GVV
30.0%
YTD GW
BPP GOAL 45.9%
20.0%
Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11
Month
WATER SUPPLY
FY 2010-2011
January 2011 Water Supply
IMPORT
24.3%
GW
75.7%
2010-2011 YTD Water Supply
GW
37.5%
IMPORT
62.5%
GW BPP GOAL
45.9%
TOTAL WATER USE
FY 2010-2011
3,000
Monthly Average Mean Temperature (°F) ■09-10GW
73.6 009-10 IMPORT
72.2
■08-09 GW
2,500 72.1 008-09IMPORT
69.8 ■10-11 GW
74.0 74.373.2
69.7 74.1 010-11 IMPORT
70.8 65.9 67.2
2,000 62.9 66.4
61.6
66.1
62.6
L% I
Q
1,500 62.6 58.2 59.3
E 65.4
E 61.5
> 60.2
55.8 60.0
54.3 58.2
1,000 56.4 56.3
57.2
500
0
o~ o~' 0300 N", oo' @ NQ1 (Z' @ NQ1 o~' N° o° N° NN NQ5 NQ) N° NN
~A' ~A ~A'
Month
FY 2010-2011 YTD Water Supply
22,000
Budgeted Total GW + Import
20,000
Actual Total GW + Import
18,000 --rrBPP GW Goal 45.9%
16,000 Actual GW Production
14,000 -
U-
Q 12,000
m
E
0 10,000
8,000
6,000 0000A<
4,000 000001111~
2,000
0
Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11
Month
January 2011 Daily Average Demand (MG)
16.0
14.0 13.5
11.5 12.3 12.1 12.1 12.4
12.0 11.2 _
10.0
8.0
6.0
4.0
2.0
0.0
~J~aaa o~a~a J~yaaa ~~yaaa ~~`'aaa ~`aaa ~~aaa
ITEM NO. 2.3
AGENDA REPORT
Meeting Date: February 3, 2011
To: Planning-Engineering-
Operations Committee
From: Ken Vecchiarelli, General
Manager
Presented By: Lee Cory, Operations Manager
Prepared By: John DeCriscio, Chief Plant
Operator
Subject: 2011 MWD Shutdown
SUMMARY:
The Metropolitan Water District of Southern California (MWD) has scheduled a shutdown of the
Robert B. Diemer Treatment Plant and its influent and effluent transmission pipelines from 12:01
A.M. on Sunday, February 27, 2011 through midnight on Saturday, March 5, 2011. The purpose of
the shutdown is to construct treatment facility improvements and to perform critical pipeline
maintenance. During this period, the Yorba Linda Water District will not have access to imported
water supplies, which typically make up over 50% of its water supply resources overall. These
resources normally supply 100% of the water demands to the eastern sections of the District's
service areas (to the Hidden Hills area and eastward) and to elevations served above the 780
Pressure Zones. In preparation for the 2011 MWD System Shutdown, the Production Division has
developed an operating plan that strives to achieve uninterrupted water service to our customers
throughout the shutdown period. Attached is a staff report outlining this plan and the actions
initiated prior to the shutdown.
ATTACHMENTS:
Name: Description: Type:
MEMORANDUM MWD Shutdown.docx Memorandum - Operations Plan Backup Material
Yorba Linda
Water District
MWD Shutdown Operational Preparation
DATE: January 26, 2011
TO: Ken Vecchiarelli, General Manager
FROM: John DeCriscio, Chief Plant Operator
COPY Lee Cory, Operations Manager
All Production Operators
Damon Micalizzi, Public Information Specialist
SUBJECT: Operating Plan for 2011 Seven Day Metropolitan Water District (MWD)
Shutdown. (12:01 A.M. February 27, 2011 through midnight March 5, 2011)
The Metropolitan Water District of Southern California (MWD) has scheduled a
shutdown of their Diemer Filtration Plant in Yorba Linda, along with major transmission
pipelines to and from this facility. This shutdown has been scheduled to construct
treatment facility improvements and to facilitate critical pipeline maintenance. In
preparation for this shutdown, the YLWD Production Division has evaluated our
groundwater delivery facilities and current water system demands. We have developed
a plan to achieve uninterrupted service to our customers during the seven day MWD
shutdown, which includes the following:
1. Evaluation of Current Demands. During the past two weeks our water demands
averaged approximately 15 million gallons per day (MGD), with 3.5 MGD of these
demands supplied from MWD connections. We will monitor the weather forecast for
the weeks leading up to the shutdown. We have identified areas of potential
shortfalls if demands increase or if the shutdown has to be extended beyond the
seven days.
2. YLWD System Preparation. In preparing for the MWD shut down, Production staff
has evaluated our system to determine operational conditions. The following is a list
of system conditions at the time of this report and the expected conditions during the
shutdown period.
• Well No. 1 is scheduled to be out of service and will not to be available during
this shutdown.
1
• The District's eight other wells, with a combined capacity of 11,000 gpm, are
operational and available.
• We will fill all reservoir storage to near full capacity immediately prior to the
shutdown.
• We have installed and tested a portable pump at the Fairmont Reservoir and
Booster Pump Station site. This pump is available to supply an additional
1,500 gallons per minute (gpm) from Pressure Zone 3 (675 feet above mean
sea level) to Pressure Zone 4 (780 feet above mean sea level).
The following notifications are planned:
3. Public Notification of the shutdown. Production staff will notify Black Gold Golf
Club of this shutdown with a letter sent as a follow up.
• The City of Yorba Linda will be notified of the shutdown by written
correspondence (i.e. a letter).
• Placentia Yorba Linda School District will be notified in writing.
• The District's two portable message boards will be serviced to ensure they
will be available if needed.
• A notification will be on the District's web site.
• It may be necessary to ask our customers for additional conservation efforts.
This effort will depend on water demands and weather conditions leading up
to the shutdown.
4. Temporary Water Service Interruptions (Irrigation and Construction Water
Services). If demands are exceeding planned estimates and water supplies from
storage reservoirs are showing signs of rapid depletion, non-essential irrigation and
water used for construction purposes may be temporarily halted for the duration of
the MWD shutdown. This interruption of non-essential water use will be
accomplished cooperatively through the City Public Works and Park and
Recreations Departments and/or by manually turning off service at the meters or
irrigation backflow devices if necessary.
2
ITEM NO. 2.4
AGENDA REPORT
Meeting Date: February 3, 2011
Subject: Monthly Preventative Maintenance Program Report (To be provided at the
meeting.)
ATTACHMENTS:
Narn9: Doscrip ion: u
PM Report.pdf Monthly Report Backup Material
PM PROGRAM
20010/2011
Fiscal 20010-11 JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN
Percent of target 8% 17% 25% 33% 42% 50% 58% 67% 75% 83% 92% 100%
HYDRANTS (3,881) Target; all hydrants to be serviced annually.
INSPECTED THIS MONTH 55 293 160 446 552 589 337
INSPECTED THIS YEAR 55 348 508 954 1,506 2,095 2,432
% OF TOTAL 1.4% 9.0% 13.1%1 24.6% 38.8% 54.0% 62.7%
VALVES (10,70612=5,353) Target; all valves to be operated every two years
OPERATED THIS MONTH 536 378 380 457 343 315 414
OPERATED THIS YEAR 536 914 1,294 1,751 2,094 2,409 2,823
% OF TOTAL 10.0% 17.1%1 24.2% 32.7% 39.1%1 45.0% 52.7%
DEAD ENDS (155 X 2 = 310) Target; all dead ends to be flushed twice each year.
FLUSHED THIS MONTH 0 0 0 0 155 0 0
FLUSHED THIS YEAR 0 0 0 0 155 155 155
% OF TOTAL 0.0% 0.0% 0.0% 0.0% 50.0% 50.0% 50%
AIR VACS (309) Target; all air/vacs to be serviced annually.
INSPECTED THIS MONTH 296 13 2 0 0 0 0
INSPECTED THIS YEAR 296 309 311 311 311 311 311
% OF TOTAL 95.8% 100.0% 100.7% 100.7% 100.7% 100.7% 100.7%
PRVs (150) 40 STATIONS Target; all PRVs to be serviced annually.
INSPECTED THIS MONTH 0 12 16 31 42 38 34
INSPECTED THIS YEAR 0 12 28 59 101 139 173
OF TOTAL 0.0% 8.0% 18.7% 39.3% 67.3% 92.7% 115.3%
PM PROGRAM
20010/2011
Fiscal 20010-11 JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN
Percent of target 8% 17% 25% 33% 42% 50% 58% 67% 75% 83% 92% 100%
SEWER CLEANING (802,560) Target; all sewers to be cleaned annually.
CLEANED THIS MONTH 126,497 68,133 38,676 46,790 73,169 82,782 97,798
CLEANED THIS YEAR 126,497 194,630 233,306 280,096 353,265 436,047 533,845
% OF TOTAL 15.8% 24.3% 29.1%1 34.9% 44.0% 54.3% 66.5%
SEWER TELEVISING (200,640) Target; all sewers to be televised every 4 years.
TELEVISED THIS MONTH 12,176 18,676 6,524 14,128 201 -
TELEVISED THIS YEAR 12,176 30,852 37,376 51,504 51,504 51,705 51,705
% OF TOTAL 6.1%1 15.4% 18.6% 25.7% 25.7% 25.8% 25.8%
OTHER SEWER WORK.
S.S. OVERFLOWS 0 0 0 0 0 0 0
SERVICE CALLS 1 0 0 1 1 2 0
REHAB FOOTAGE 0 0 0 319 0 272 0
MAIN REPAIRS 0 0 0 3 629 1 1
MANHOLE REPAIRS 0 4 16 1 2 1 0
ITEM NO. 2.5
AGENDA REPORT
Meeting Date: February 3, 2011
Subject: Status Report on Capital Projects in Progress
ATTACHMENTS:
Name: Dosciiption: a ype:
CIP Rept Feb2011.pdf Status Report on Capital Projects in Progress Backup Material
CAPITAL IMPROVEMENT PROJECTS STATUS REPORT
Date: February 1, 2011
New Information since Last Report is Shown in Red
IN CONSTRUCTION
Project Current Status Next Actions Comments
1 Wells 1, 5 and 12 Upgrade W-5 & -12 refurbishments Contractor expected to receive Attempting to complete W-1 work
Budget: $190,000 Job No. 200813 complete. W-1: selected low- and install new pump in February before MWD shut-
Project Contact: Anthony Manzano quote contractor; new pump assembly and gear drive by down (however, availability of W-1
Project Completion: TBD ordered. late February to early March. is not critical for the shutdown)
2 Highland Booster Station Upgrade Contractor mobilized & began Excavation for building Project construction period is 13.5
Budget: $5,000,000 Job No. 200814 installation of shoring for footing, pump cans and meter months, with completion estimated
Project Contact: Joe Polimino building foundation. Started vault. Continue to work on December 2011.
Planned Completion Date: Dec. 2011 staircase to reservoir top. staircase.
3 VDV Valve Replacement Ph 2 & 3 Contract agreement approved Set up pre-const. meeting with Construction expected to begin
Budget: $600,000 Job No. 200908 and fully executed. Submittal Contractor and District to early in March 2011. This is sooner
Project Contact: Derek Nguyen for materials also approved. coordinate proper shutdown than the original estimated schedule.
Planned Completion Date: May 2011 and construction.
4 Emergency Pump-out Facilities & Pre-construction meeting Issue Notice to Proceed and Construction completion expected
Anaheim Intertie Connection scheduled first week of Feb. review construction schedule mid-summer 2011.
Budget: $500,000 Anaheim Public Works to be for start date.
Job No. 200903 & 200906 invited. Reviewing shop
Project Contact: Joe Polimino drawings for both projects.
Planned Compl. Date: Summer 2011
5 Mixers in Hidden Hills Reservoir Insurance documents submitted GM signs contract agreement. Plan to complete installation by
Budget: $75,000 Job No. 2010-25 to attorney for approval. after attorney's approval and March 2011.
Project Contact: Derek Nguyen Contractor needs to mare supplier is authorized to
Planned Completion Date: Feb 2011 minor revisions, proceed.
1
IN DESIGN
Project Current Status Next Actions Comments
1 Ohio/Oriente Pipeline Replacement Reviewed project with City of 100% design submittal due Construction completion anticipated
Budget: $530,000 Job No. 201005 YL. Held Jan. 20 public early Feb. Presentation at Jan. by summer 2011.
Project Contact: Anthony Manzano outreach meeting to discuss 27 City Traffic Commission
Planned Completion Date: Sept. 2011 impacts to residents. meeting.
2 Well 20 Equipping 90% design reviewed and 100% design submittal due by Anticipate going out to bid March
Budget: $2,000,000 Job No.200711 submitted to consultant. end of January. 2011 with construction completion
Project Contact: Anthony Manzano summer 2011.
Planned Completion Date: Sept. 2011
3 Lakeview Grade Separation Staff reviewing prior-rights Resolve prior-rights issues and 100% design submittal from OCTA
Budget: TBD Job No. 201002 issue with legal counsel. complete cost-sharing expected in March or April.
Project Contact: Anthony Manzano Submitted 65% design review Agreement w/OCTA.
Planned Completion Date: Sept. 2013 comments to OCTA's
consultant.
4 2010 Waterline Replacement Project Plumosa Dr. preliminary Plumosa Dr. 70% design Plumosa Dr. construction
Budget: $2M Job No. 201012 design reviewed with City of submittal anticipated in March. anticipated for summer 2011.
Project Contact: Anthony Manzano YL. Survey work underway Preliminary design for other Const. for other sites expected to
Planned Completion Date: Dec. 2011 for remainder of six sites. sites due in April. start fall 2011.
5 YL Blvd. BPS & Pipeline Kickoff design meeting with Begin CEQA and Conditional Meet with City to discuss issues and
Budget: TBD Job No. 200817 Lee & Ro, Inc. set for Jan. 27, Use Permit application. PDR concerns for CUP and CEQA.
Project Contact: Hank Samaripa 2011. to follow.
Planned Completion Date: Dec 2012
2
IN PLANNING
Project Current Status Next Actions Comments
1 Fairmont BPS & Site Improvements Final agreement being Confirm Fairmont site May have agreement for
Budget: TBD Job No. 200803 executed by Shapell for partial redevelopment plan and consideration by PEO and Board in
Project Contact: Anthony Manzano payment for construction of prepare RFP for design. March.
Planned Completion Date: TBD site improvements.
2 Recycled Water Study Draft report submitted to Work on incorporating review District is in process of applying for
Budget: $1,800,000 Job No. 200807 SWRCB was approved. comments from the State into 50% grant disbursement in the
Project Contact: Derek Nguyen District meeting with potential Final Report and submit to the amount of $37,500 as approved by
Planned Completion Date: TBD users to solicit letters of State for mid-course review. State. Remaining balance disbursed
interest as part of study. prior to finalizing report. upon approval of Final Report.
3 West Wellfield Project Investigating potential well Contact OCWD to determine if May retain a Property Acquisition
Budget: $9,000,000 Job No. 2009-22 sites east of Tustin Avenue. they will sale small well site Firm for assistance and explore
Project Contact: Anthony Manzano OCWD's contract w/developer near Well 20. other sites.
Planned Completion Date: TBD near basins expired.
4 Sewer Master Plan Draft report received Dec 15 Model, report and model- District staff requested proposal for
Budget: $350,000 Job No. 200916 and District provided training expected to be Master Plan addendum for potential
Project Contact: Anthony Manzano comments. complete by February. addition of the City of YL's existing
Planned Completion Date: Oct. 2010 sewer.
5 Elk Mountain Site Improv Study Completed Turf 101 Class and Workshop Jan 27 to review Review feasibility study and
Budget: $300,000 Job No. 200522 tour of parks & athletic fields and comment on two options evaluate site development options
Project Contact: Hank Samaripa with artificial turf. for the Elk Mountain site. and costs for each.
Planned Completion Date: Dec 2011
6 OC-51 Connection Upgrade District provided revised MWDOC to administer further Will consider next steps after
Budget: $242,000 Job No. 200815 construction cost estimate to discussion with MWD receiving feedback from MWD and
Project Contact: Derek Nguyen MWDOC for further regarding District direction MWDOC.
Planned Completion Date: TBD discussion with MWD. with modifications and cost.
7 Urban Water Management Plan Determined the Gallons Per Staff to review final 2010 Submit final 2010 UWMP by July
Budget: $20,000 Job No. 2201013 Capita per Day demand per UWMP Plan. Present to PEO L 2011 to State Dept. of Water
Project Contact: Hank Samaripa SB7x-7 conservation law and and Board. Resources.
Planned Completion Date: June 2011 include in UWMP.
3
ITEM NO. 2.6
AGENDA REPORT
Meeting Date: February 3, 2011
Subject: Groundwater Producers Meeting Report
ATTACHMENTS:
Name: cv, i~a$icri: a ype:
GWP Minutes 011211.pdf GWP Meeting Report for January 2011 Backup Material
Yorba Linda
Water District
MEMORANDUM
DATE: January 14, 2011
TO: Ken Vecchiarelli, General Manager
FROM: Steve Conklin, Engineering Manager
COPY: Pat Grady, Assistant General Manager
Lee Cory, Operations Manager
John DeCriscio, Chief Plant Operator
SUBJECT: Groundwater Producers Meeting, January 12, 2011
1 attended the Groundwater Producers (GWP) Meeting on January 12 at OCWD. A
summary of each item discussed is as follows:
1. Water Quality Update. OCWD staff provided an update on water quality issues
including the following:
a. Revised Reporting Levels for 1-4 Dioxane. As OCWD reported at the
December GWP meeting, new advisory levels were issued by CDPH in
November for the chemical 1-4 Dioxane (1-4-D). The Notification Level
was reduced from 3 parts per billion (ppb) to 1 ppb, and the Response
Level from 300 to 35 ppb. In 2001, low levels were found in wells of
Newport Beach, Fountain Valley, Mesa Consolidated WD, and IRWD. No
1-4-D was found above the detection level for the wells of YLWD at that
time or since.
b. New Draft Public Health Goal (PHG) for Chromium-6 (CrVI). The State
issued a reduced PHG of 20 parts per trillion (ppt) on December 31, 2010.
A PHG is an advisory level, not an enforceable regulatory standard. The
Department of Public Health is now tasked with establishing the
appropriate MCL for CrVI which could take two to three years. Currently
YLWD wells have an average of 0.1 ppb CrVI. This concentration is below
the required detection limit of 1.0 ppb.
c. State is soliciting comments on a proposed revised PHG for
Perchlorate at 1.0 ppb. The existing PHG and MCL is 6.0 ppb. YLWD
has an average Perchlorate concentration of less than 2.5 ppb.
d. U.S. Dept of Health & Human Services is recommending that fluoride
in drinking water be no more than 0.7 parts per million (ppm).
YLWD's groundwater has an average of 0.50 ppm. The imported water
from MWD has a fluoride concentration of 0.7-0.9 ppm.
1
2. Final Review of "Transparency in Government" Letter. As reported by
OCWD in December, the OCWD Board is requesting support from all
Groundwater Producers for a letter they propose to send to Governor Brown,
stating that "OCWD and its local groundwater producers, representing 2.4 million
residents in north and central Orange County, support recent government reform
measures in response to the City of Bell salary scandal and encourage
immediate action to pass measures increasing government compensation
transparency during this legislative session." OCWD staff noted that this letter
and the support of the Groundwater Producers is requested to increase
accountability and restore public faith in state and local government (including
special districts). There were no further comments at the January 12 meeting;
therefore, the letter will be finalized and sent to the governor.
3. Update on Santa Ana River and Prado Dam Recharge Activities. OCWD
reported on the effect of the December 2010 storms, in which there were 8
inches of rain in six days, and a record total of 10.5 inches for the month
measured at OCWD Field Headquarters in Anaheim. In late December, there
was a record-volume of 100,000 acre feet behind Prado Dam. The Army Corps
limited discharge from the dam to 3,000 cfs (i.e., 6,000 AF/day) to minimize scour
of the river bed and protect the SARI sewer main buried below. Storage behind
Prado is currently in the range of 10,000 AF. Discharge from the dam will be
reduced to 300-500 cfs for diversion from the river to the District's recharge
basins. It was also noted that Irvine Lake topped out and is spilling to Santiago
Creek, which filled and topped out the District's Santiago Recharge Basins in
Orange with 11,000 AF. In closing they noted, that while December was record-
breaking there is no guarantee that the rains will continue. The current prediction
from the National Weather Service is for dryer than normal weather patterns over
the next three months.
4. Preparation of BPP and RA Projections for FY 2011-12. OCWD reported that
they project the BPP to be 62-65% and the RA to be $255-265 next FY. There
will be more detailed information and perhaps a better estimate on the District's
website on January 14.
5. FY 2011-12 Budget-Preparation Schedule. OCWD reported that the District's
draft budget for next FY will be presented to the Board on March 2 and to the
GWP on March 9. Major issues impacting the budget are 7.5% MWD rate
increase in January 2012 and the need for higher OCWD rates if the Board
approves proceeding with the 30 MGD expansion of GWRS Project.
6. MWD Discounted Replenishment Water Discussion. OCWD reported that
snow pack is about 200% of normal and many of the reservoirs in the state are
much higher than before. MWD may be looking for ways to sell more water and
get more into storage. In the past, MWD offered water for replenishment at
discounted rates during wet years. OCWD is pursuing this, but it is doubtful due
to political and other issues. Updates will follow in the months ahead.
7. Discussion of Annexation Request Issues. Information was provided and
discussed on the following issues:
a. Current and Future Sources of Water for GW Basin Recharge.
OCWD provided a handout showing recharge supplies of approximately
2
294,000 AF/yr in 2011 and 347,000 AF/yr in 2035. The latter figure
includes the first 30,000 AF expansion of GWRS but not the potential final
30,000 AF expansion.
b. Current and Future Recharge Capacity. OCWD noted that they will
continue to pursue cost-effective projects to expand recharge capacity but
did not elaborate due to time constraints.
c. Future Total Water Demands. OCWD provided a handout showing total
water demands (met by import and groundwater) of 455,000 AF/yr in
2012. For 2035, they showed additional demands of 68,000 AF/yr due to
infill, 15,100 AF/yr from current annexation request, and 27,000 AF/yr for
ultimate build-out in IRWD. The combined total of 565,100 AF/yr is
viewed as the projected ultimate demand by the groundwater producers, if
all annexation requests are approved.
d. Estimated Imported Water Connection Capacity. OCWD provided a
handout prepared by MWDOC showing the MWD connection capacity of
each groundwater producer in cfs and AF/yr and compared that to the
total water demand of each agency. In all cases, the MWD delivery
capacity exceeded the total water demand, indicating that each can meet
demand from MWD supply even if the BPP is significantly reduced.
However, it was noted that this could come at higher costs and with
potential penalties by MWD.
e. Other. OCWD noted that at the next Annexation Workshop, they will
provide an estimate of the BPP with and without annexation demands.
3
ITEM NO. 3.1
AGENDA REPORT
Meeting Date: February 3, 2011 Budgeted: Yes
Total Budget: $5.5 Million
To: Planning-Engineering- Cost Estimate: $220,000
Operations Committee
Funding Source: Water Revenue Bond
From: Ken Vecchiarelli, General Account No: 101-2700
Manager
Job No: J-200814
Presented By: Steve Conklin, Engineering Dept: Engineering
Manager
Reviewed by Legal: No
Prepared By: Joe Polimino, Project Engineer CEQA Compliance: MND
Subject: Amendment No. 3 to MWH Americas Professional Services Agreement -
Construction Support Services for the Highland Booster Pump Station
Replacement
SUMMARY:
Construction of the new Highland Booster Pump Station (BPS) commenced in December and is
proceeding on schedule. District staff and the project team determined that construction support
services are needed from MWH, which were not included in the original scope of work for the
Professional Services Agreement (PSA). At the District's request, MWH prepared a proposal for
additional construction support services, which staff has reviewed and recommends for approval.
STAFF RECOMMENDATION:
That the Committee recommend the Board of Directors approve Amendment No. 3 to the
Professional Services Agreement (PSA) with MWH Americas, in the amount of $219,791, for
additional construction support services for the Highland Booster Pump Station Replacement and
Expansion Project, Job No. 200814.
DISCUSSION:
When the Request for Proposals (RFP) was initially prepared by District staff for the new pump
station project, the Scope of Work included primarily the engineering design services and limited
Construction Phase Services. It was understood by District staff that this was a minimum level of
services and that a considerably greater effort would be required, due to the anticipated complexity
of the project. The full scope of Construction Phase Services required could not be accurately
determined until after the design criteria was approved by the project team and the design was
completed relative to mechanical equipment, electrical systems, control systems, and other project
elements.
The purpose of including a basic or minimum level of Construction Management (CM) services in
the RFP was to have the proposing firms provide information on their proposed CM staff, approach,
experience and staff hours per task. This information helped YLWD staff determine the
qualifications and capabilities of the proposing firms to perform all of the necessary tasks for the
project, from permitting through design and construction management. These efforts assisted in the
selection of MWH Americas as the District's preferred consultant for the project.
After the completion of design, award of the construction contract, and receipt of initial shop
drawings from the construction contractor, it was possible to more accurately project the extra work
hours and tasks required for CM beyond those listed in the original RFP. Following discussions
between District and MWH staff regarding necessary CM tasks and level of effort, MWH submitted
a letter proposal describing the additional tasks, hours and fee, a copy of which is attached.
In summary the additional tasks would include the following:
Submittals/Shop Drawings. The original PSA includes review of 30 submittals and shop drawings.
The amendment includes services for an additional 45 submittals.
Requests for Information (BFI's). The original PSA includes review of 12 RFI submittals. The
amendment includes services for an additional 48 submittals.
Change Order Preparation. The original PSA did not include these services. The amendment
budgets 100 hours to draft and process change order documents.
Review Change Requests. The original PSA did not include these services. The amendment adds
80 manhours to review change order requests from the contractor.
Meetings. The original PSA included 9 meetings. The amendment includes 8 additional meetings.
Southern California Edison Permit Coordination. MWH will subcontract with RBF Consulting
(the project electrical engineer) to continue their support of the SCE Generating Facility
Interconnection Application in accordance with SCE Rule 21. Added is $8,520 for this task.
Instrumentation and Programming Support. The original PSA did not include support relating to
the control systems, programming of the PLC and Wonderware software development. Added is a
subcontract under MWH with MSO Technologies for $20,000.
Specialty Inspections. The original PSA did not include support for special inspections, including
electrical and instrumentation. MWH will provide an electrical and instrumentation engineer to
observe and inspect installations as needed. Added is $22,840 for this task.
Final Inspection and Startup. MWH will assist the District in the final walk through with inspection
of the electrical, instrumentation and startup of the engines, motors and pumps. The amendment
adds $21,033 for this task.
If approved, Amendment No. 3 for $219,791 will increase the PSA total from $587,027 to $806,818.
Within that total, the tasks and fee for CM Services will increase from $60,000 to $279,791. That
total equates to approximately 6.2% of the $4,525,800 construction cost. This percentage compares
very favorably to other recent complex construction projects completed, including 6.5% for CM for
the Lakeview Booster Station, 6.4% CM for the Highland Reservoir, and 6.9% CM for the Hidden
Hills Reservoir construction.
District staff has reviewed the proposed change order and discussed it with staff of MWH. Staff
believes that the proposed scope and fee are necessary and appropriate for the additional services
and recommend approval of Amendment No. 3 for $219,791.
PRIOR RELEVANT BOARD ACTION(S):
On July 9, 2009, the Board of Directors approved the award of the Professional Services
Agreement for the Highland Booster Pump Station Replacement Project to MWH Americas, for a
fee not to exceed $469,593. On January 28, 2010 the Board of Directors approved Amendment No.
1 for a fee not to exceed $91,940. On February 11, 2010 the Board of Directors approved
Amendment No. 2 for a fee not to exceed $18,929.
ATTACHMENTS:
Name: Description: V Ype:
Addendum 3 Exhibit _A Scope of Work.docx MWH Scope of Work Exhibit A Backup Material
YLWD Add 3rev5 (2).pdf Exhibit B Cost Breakdown Backup Material
MWH
BUILDING A BETTER WORLD
EXHIBIT A
SCOPE OF WORK
The project construction for Highland Booster Station Replacement is expected to require
approximately thirteen (13) months of as-needed support. The estimate below is based
on overall completion of the contract for engineering services during construction.
Record drawing preparation is included in our original contract. If the construction
contract period extends beyond thirteen months from the notice to proceed, adjustments
for inflation for work performed after that date may be required for work aside from
preparation of record drawings.
MWH will review shop drawings for the project for conformance with the contract
documents. Our contract included some submittals. We are requesting a budget for an
additional 45 submittals. MWH will provide a written response to each of the shop
drawings with a recommendation for the contractor's next course of action. Quotation of
hours and cost is based on an estimated average of 4 hours of review and processing
time for original submittals. It is estimated that 10 submittals will be resubmitted to
incorporate comments from the review of the initial submittal. Each re-submittal will
require an estimated 1.5 hours of review and processing time.
MWH will respond to written requests for information/clarification from the contractor
during construction. Our contract included 12 RFI's. We are requesting budget for an
additional 48 RFI's. It is assumed that MWH will respond to 60 RFIs during the course of
the project. Quotation of hours and cost is based on an estimated average of 4 hours of
review and processing time.
MWH will issue Contract drawing Clarification, as requested by the District to support
construction activities. We will notify the District of any such requested deviations or
substitutions and when necessary provide the District with a recommendation concerning
the same. MWH will prepare change orders during the construction of the project. It is
estimated that 100 hours may be required to draft and process change order documents
during the course of the project. Our contract did not include a budget for change order
preparation or review.
MWH will review change order requests to support the District. Change order requests
will be reviewed for compliance with the contract documents and reasonableness of
cost/time estimates. MWH will respond to requests directly to the District. It is estimated
80 hours for review of contractor change orders.
19900 MacArthur Blvd. TEL 949-328-2400
/ Suite 250 FAX 949-328-2448
Irvine, California 92612 www.mwhglobal.com
YLWD -2- January 24, 2011
MWH will attend project meetings and site visit at the request of the District during the
construction. It is assumed that one kick-off meeting, fifteen (15) site visits/meetings and
a concrete conference will be held during the construction of the project. Two MWH staff
are budgeted for each meeting. Our contract included nine (9) meetings during
construction. MWH will attend these additional 8 meetings, as requested by the District.
MWH will subcontract with RBF to continue their support of the SCE Generating Facility
Interconnection Application in accordance with SCE Rule 21. The contractor will require
additional information during the submittal process to make the application. RBF will
assist the contractor by responding to questions from SCE. It is assumed one meeting
will be held at the project site with SCE.
MWH will subconsult with MSO Technologies Inc. to provide support to the District
relating to questions on the control systems, programming of the PLC and Wondware
development. MSO will support the District in the review of design questions,
instrumentation calibration questions and meetings.
The District will require assistance during construction in performing inspection of the
electrical and instrumentation systems. MWH will provide an electrical and
instrumentation engineer to observe and inspect the installation of the electrical and
instrumentation. It is assumed there will be no factory inspection of the motor control
center of electrical cabinets. MWH may also perform up to 80 hours of special inspection
of the mechanical equipment during construction. The equipment will be inspected in the
field prior to installation.
The District will require special inspection at the completion of construction for
development of a final punchlist. MWH will assist the District in the final walk through with
inspection of electrical and instrumentation. The mechanical engineer will also be
present during the startup of the engines, motors and pumps. It is assumed four
engineers will be present during the walk through. It is estimated the final inspection will
be one-day with a follow-up meeting at the District.
Pump station startup will require support by the electrical engineer and mechanical
engineer to witness startup and assist in adjustments to mechanical and electrical
equipment.
Exhibit B
Proposed Budget
Task Principal Principal Senior Senior Professional Subconsult Total
Professional Engineer Designer Addendum 2
235 220 155 150 135
1. Shop Drawings 60 60 40 40 $33,900
RBF $12,880 $12,880
2. RFI's 2 80 120 $36,070
RBF $3,680 $3,680
3. Change Order Preparation 20 40 40 $16,000
RBF $3,478 $3,478
4. Review Contractor Change Requests 2 40 40 $15,470
$0
5. Meetings 2 40 40 $15,470
RBF $3,680 $3,680
6. SCE Permit Coordination 16 $3,520
$5,000 $5,000
7. Instrumentation and Programming Support 16 16 2 $6,270
MSO $20,000 $20,000
8. Special Inspections 30 80 $19,000
RBF $3,840 $3,840
9. Final Inspection and Startup 2 24 48 $13,190
RBF and MSO $7,843 $7,843
Other Direct Cost $500
Total 8 326 324 160 82 $60,401 $219,791