HomeMy WebLinkAbout2012-02-07 - Planning-Engineering-Operations Committee Meeting Minutes MINUTES OF THE
YORBA LINDA WATER DISTRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
February 7, 2012
A meeting of the Planning-Engineering-Operations Committee was called to order by
Director Collett at 11 :00 a.m. The meeting was held at the District's Administrative
Office at 1717 E Miraloma Ave, Placentia CA 92870.
COMMITTEE STAFF
Director Ric Collett, Chair Ken Vecchiarelli, General Manager
Director Robert R. Kiley Steve Conklin, Engineering Manager
Lee Cory, Operations Manager
1. PUBLIC COMMENTS
None.
2. ACTION ITEMS
2.1. Rejection of Claim for Ohio/Oriente Pipeline Project
Mr. Conklin reported that construction is essentially complete and all
facilities are in operation for the subject project. He noted that in July
2011, prior to the start of construction, the contractor, Mamco
Construction, submitted Change Order Request No. 1. That request was
denied by the District. Thereafter, Mamco did not file a written protest to
the District's denial as required by the contract. On January 24, 2012,
Mamco submitted a claim for extra work at the end of the construction
project. District staff reviewed that claim and determined that it described
the same issues raised in Change Order Request No. 1. Following
discussion, the PEO Committee supported the staff recommendation that
the new claim by Mamco be denied by the Board because the items in the
claim were previously denied by the District and Mamco did not file a
written protest to such denial as required by the contract.
2.2. Adopt 2012 Orange County Regional Water and Wastewater Multi-Hazard
Mitigation (Hazmit) Plan Update
Mr. Conklin reported that the five-year update to the subject Hazmit Plan
has been completed through MWDOC. Participation by District staff in the
update makes it possible for the District to remain eligible for FEMA
mitigation funding in the event of a declared emergency. Following
discussion, the Committee supported the staff recommendation that the
Board adopt Resolution No. 12-03 Adopting the Hazmit Plan Update.
1
2.3. Change Order No. 1 for Well No. 20 Wellhead Equipping Project
Mr. Conklin reported that work is proceeding on construction of the subject
project. However, progress has been slowed due to delays in material
and equipment manufacturing and delivery to the project. He described
the equipment and delays, and following discussion, the Committee
supported the staff recommendation that the Board approve Change
Order No. 1 for no additional cost and 74 additional calendar days for
Pascal & Ludwig Constructors for the Well No. 20 Wellhead Equipping
Project.
2.4. Sewer Facilities Document Conversion
Mr. Conklin reported that, as part of the City of Yorba Linda east side
sewer transfer, District staff was aware that facility records needed to be
converted to electronic format. For this necessary work, staff issued an
RFP to five qualified firms and received three proposals. Staff discussed
the proposal evaluation process and the review of the qualifications of the
firm that was both top rated and had the lowest fee. Following discussion,
the Committee supported the staff recommendation that the Board
authorize execution of a PSA with that firm, Nobel Systems, for $20,960 to
provide professional services to convert facility drawings to GIS format.
2.5. Purchase of Valve Truck Assembly
Mr. Cory described the elements of the valve truck assembly and the
process to meet the District's purchasing policy for this specialty truck, to
replace the District's older vehicle. He noted that for various major
elements, cost quotes are separately received for each. Thereafter, the
District mechanics assemble the elements on a truck chassis into the
completed valve truck, at a significant savings over the purchase of a
finished vehicle from a specialty supplier. Following discussion, the
Committee supported the staff recommendation that the Board authorize
the GM to execute a purchase order for the cab and chassis assembly
and further authorize the GM to execute additional purchase orders for all
other equipment required to assemble the utility vehicle.
3. DISCUSSION ITEMS
3.1. Draft Modified CIP Budget
Mr. Conklin reported that, at the January 16 Workshop, the Board
requested that staff review the existing CIP budget, identify priority
projects, and develop a modified implementation schedule to spread the
cost over a longer time frame. In response, staff prepared a first-cut
document, which he discussed with the PEO Committee. Following
discussion, the Committee asked that staff continue to evaluate the CIP
budget and that the various potential modifications be plugged into the
District's financial model for review.
2
3.2. Monthly Preventative Maintenance Program Report
Mr. Cory reported on the status of tasks in the PM Report through January
2012. He noted that work tasks are on target with the exception of sewer
televising. For that task, we are catching up, but he noted that, when
televising, we often find roots that must be cut and cleared before we can
proceed with cleaning and camera work. This slows production, but is
necessary. Mr. Cory indicated that this is more of an issue in the sewer
lines in easement areas for the eastside sewers we accepted from the City
last July. He noted that after we complete our first pass through all of the
new eastside sewers, it should be easier to keep them up, and to our
standard.
3.3. Monthly Groundwater Production and Import Water Report
Mr. Conklin reported that our groundwater use increased to 68% in
January, up from 40% in December. This was due to the loss of import
water for 7 days due to the shutdown of the Diemer Plant, as well as our
scheduled change over to more groundwater due to the January 1 price
increase for import water. He noted that by June 30, we will achieve our
BPP goal of 48% groundwater overall for FY11-12. Mr. Conklin also
pointed out that our water demand for January was 16.5% over our
monthly projection, but for the 7 months through January, we are still 5.7%
under our projection.
3.4. Groundwater Producers Meeting Report
Mr. Conklin reported on the items discussed at the January 11, 2012
meeting.
3.5. Status Report on Capital Projects in Progress
Mr. Conklin reported on the status of capital projects in planning, design
and construction. He noted that the Yorba Linda Blvd Pipeline Project is
out to bid, with bid opening scheduled for February 15. The plan is to
award the construction project in March so that the majority of the work
can be completed this coming summer, when school is out and traffic is
lighter along this very busy corridor.
3.6. Status of Strategic Plan Initiatives
Mr. Conklin reported on the status of strategic planning objectives related
to engineering and construction.
3.7. Future Agenda Items and Staff Tasks
None.
4. ADJOURNMENT
4.1. The meeting adjourned at 12:10 p.m. The next meeting of the Planning-
Engineering-Operations Committee will be held March 1 , 2012 at 4:00
p.m.
3