HomeMy WebLinkAbout2012-07-05 - Planning-Engineering-Operations Committee Meeting Minutes MINUTES OF THE
YORBA LINDA WATER DISTRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
July 5, 2012
A meeting of the Planning-Engineering-Operations Committee was called to order by
Director Collett at 4:00 p.m. The meeting was held at the District's Administrative Office
at 1717 E Miraloma Ave, Placentia CA 92870.
COMMITTEE STAFF
Director Ric Collett, Chair Ken Vecchiarelli, General Manager
Director Robert R. Kiley Steve Conklin, Engineering Manager
Lee Cory, Operations Manager
John DeCriscio, Chief Plant Operator
1. PUBLIC COMMENTS
None.
2. ACTION CALENDAR
2.1. Terms and Conditions for Water and Sewer Service with Remarc
Management, Inc.
Mr. Conklin reported that Remarc Management, Inc. is proposing to
develop an Orchard Supply Hardware store within an existing building at
the shopping center at 17474 Yorba Linda Blvd. The new facility will
require modification to water and sewer lines serving the site. Following
discussion, the Committee supported the staff recommendation that the
Board approve proposed Terms and Conditions for Water and Sewer
Service for the proposed project.
2.2. Approval of Change Order No. 1 for Pressure Regulating Stations
Upgrade Project, Phase 1
Mr. Conklin reported that construction has begun in early July for the
Pressure Regulating Stations Upgrade Project. Submitted for
consideration is Change Order No. 1 for 27 work days and no added cost
for fabrication and delivery of the precast concrete vault for the Van Buren
site, due to changed conditions in the field. Following discussion, the
Committee supported the staff recommendation that the Board approve
C.O. No. 1 for 27 additional work days and no additional time for Vido
Samarzich, Inc for construction of the Pressure Regulating Stations
Upgrade Project.
2.3. Change Order No. 2 for Green Crest Lift Station Repairs
Mr. Conklin reported that work is proceeding on repairs and upgrades to
the Green Crest Sewer Lift Station. The contractor has completed
installation of new valves and fittings within a new vault. However, during
the pressure-washing and cleaning of the sewer wet well it was found that
1
the 23-year-old discharge piping was beginning to disintegrate and will
require replacement. Following discussion, the Committee supported the
staff recommendation that the Board approve Change Order No. 2 in the
amount of $20,745 to Pascal & Ludwig Constructors for discharge pipe
replacement for the Green Crest Lift Station Repairs Project.
2.4. Northeast Area Planning Study
Mr. Conklin reported that, following authorization by the Board, staff
issued a RFP to six firms and received four proposals for preparation of
the subject study. He described the formal process by the Review Team
to evaluate and score the proposals. Following discussion, the Committee
supported the staff recommendation that the Board authorize execution of
a Professional Services Agreement with Carollo Engineers, Inc. in the
amount of $102,883 to provide professional services to update, calibrate,
and analyze the District's water system hydraulic model and to prepare a
Northeast Area Planning Study.
2.5. Richfield Chlorine System Programmable Logic Controllers (PLC's)
Replacement
Mr. DeCriscio reported that the disinfection system operating in the
Richfield Yard produces and doses sodium hypochlorite for groundwater
pumped from on-site wells. An inspection of the 14-year—old system
indicated that the mechanical elements are in good condition. However,
the computer components are outdated, subject to failure and are no
longer available. Following discussion, the Committee supported the staff
recommendation that the Board approve the purchase of four new
Programmable Logic Controllers (PLCs) and related equipment to
upgrade the system to current standards, at a cost of $15,887.15. Further,
the new PLCs will need to be programmed by the chlorine-system
manufacturer because this is a proprietary system and they are the only
ones authorized to perform this work. It was noted by staff that it was
originally estimated that this outside programming may cost up to $18,000;
however, District staff was able to complete part of the installation in-
house, which will reduce the cost of the outside work.
2.6. Purchase of a 2012 (8-10 Yard) Dump Truck
Mr. Cory reported that the Board-approved FY12-13 Budget includes
$152,000 for the purchase of an 8-10 cubic-yard capacity dump truck.
Staff developed specifications for a vehicle with that capacity, with
airbrakes, capable of towing a trailered backhoe. Further, the specs
called for a truck durable enough to provide a long service life with a
minimum of parts inventory. He noted that bids were solicited and five
proposals were received. Following discussion, the Committee supported
the staff recommendation that the Board authorize the General Manger to
execute a contract with Inland Kenworth (Montebello) for the specified
dump truck, with a Scelzi/Paramount dump body, in the amount of
$147,639.29.
2
3. DISCUSSION ITEMS
3.1. Monthly Preventative and Reactive Maintenance Report
Mr. Cory reported that, except for Sewer Televising, all PM targets were
met for FY11-12. He noted that for Sewer Televising, we achieved 91% of
our goal, with a strong effort the last few months. Mr. Cory also noted that
our crews serviced our 40 PRV stations 2+ times this year, which is
important due to our multiple zones and hilly environment. Our new goal
for next year will be two services for all PRVs. He also noted that the
same crew that services the PRVs also services the 330 Air Vacs and the
155 Dead-Ends. Mr. DeCriscio reported on the Water Production
Summary Report for June 2012. He noted that for the month, our max
demand day was 28.1 MG and our minimum demand day was 16.6 MG,
with an average demand of 23.1 MG.
3.2. Monthly Groundwater Production and Purchased Import Water Report
Mr. DeCriscio reported that for June, our water use was 12.4% under our
budgeted projection, of which 49.2% was groundwater. He also noted that
we achieved our BPP Goal of 48.1% as of June 30, 2012.
3.3. Groundwater Producers Meeting Report
Mr. Conklin reported on items discussed at the June 13 Groundwater
Producers meeting at OCWD.
3.4. Status Report on Capital Projects in Progress
Mr. Conklin reported on the status of capital projects currently in planning,
design and construction.
3.5. Status of Strategic Plan Initiatives
Mr. Conklin reported on the status of the above that relate to engineering
and operations.
3.6. Future Agenda Items and Staff Tasks
The Committee asked that staff prepare a short presentation to the
Committee or to the Board on recent and planned preparation for the
upcoming fire season.
4. ADJOURNMENT
4.1. The meeting adjourned at 5:38 p.m. The next meeting of the Planning-
Engineering-Operations Committee will be held Thursday, August 2, 2012
at 4:00 p.m. However, the Committee commented that they are
considering moving the meeting time to starting at 3:00 pm.
3