HomeMy WebLinkAbout2012-09-06 - Planning-Engineering-Operations Committee Meeting Agenda Packet Yorba Linda
Water District
AGENDA
YORBA LINDA WATER DISTRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
Thursday, September 6, 2012, 3:00 PM
1717 E Miraloma Ave, Placentia CA 92870
COMMITTEE STAFF
Director Ric Collett, Chair Steve Conklin, Acting General Manager
Director Robert R. Kiley Lee Cory, Operations Manager
1. PUBLIC COMMENTS
Any individual wishing to address the committee is requested to identify themselves and state the matter on
which they wish to comment. If the matter is on this agenda, the committee Chair will recognize the individual for
their comment when the item is considered. No action will be taken on matters not listed on this agenda.
Comments are limited to matters of public interest and matters within the jurisdiction of the Water District.
Comments are limited to five minutes.
2. ACTION CALENDAR
This portion of the agenda is for items where staff presentations and committee discussions are needed prior to
formal committee action.
2.1. Approval of Change Orders No. 4 & 5 for Pressure Regulating Stations Upgrade Project,
Phase 1
Recommendation: That the Committee recommend the Board of Directors approve
Change Orders No. 4 & 5 for one additional work day and $3,303.18 to Vido
Samarzich, Inc. for construction of the Pressure Regulating Stations Upgrade
Project, Job No. 201108.
2.2. Approval of Change Order No. 6 for Pressure Regulating Stations Upgrade Project,
Phase 1
Recommendation: That the Committee recommend the Board of Directors approve
Change Order No. 6 for two additional work days and $7,208.91 to Vido Samarzich,
Inc. for construction of the Pressure Regulating Stations Upgrade Project, Job No.
201108.
3. DISCUSSION ITEMS
This portion of the agenda is for matters such as technical presentations, drafts of proposed policies, or similar
items for which staff is seeking the advice and counsel of the Committee members. This portion of the agenda
may also include items for information only.
3.1. Status of Meter Program
3.2. Monthly Groundwater Production and Purchased Import Water Report (To be provided at
the meeting.)
3.3. Monthly Production Division Report (To be provided at the meeting.)
3.4. Monthly Preventative Maintenance Report (To be provided at the meeting.)
3.5. Chlorine System Project Status Report
3.6. Groundwater Producers Meeting Report
3.7. Status Report on Capital Projects in Progress
3.8. Status of Strategic Plan Initiatives
3.9. Future Agenda Items and Staff Tasks
4. ADJOURNMENT
4.1. The next meeting of the Planning-Engineering-Operations Committee will be held
October 4, 2012 at 3:00 p.m.
Items Distributed to the Committee Less Than 72 Hours Prior to the Meeting-
Pursuant to Government Code section 54957.5, non-exempt public records that relate to open session agenda items
and are distributed to a majority of the Committee less than seventy-two (72) hours prior to the meeting will be available
for public inspection in the lobby of the District's business office located at 1717 E. Miraloma Avenue, Placentia, CA
92870, during regular business hours. When practical, these public records will also be made available on the District's
internet website accessible at http://www.ylwd.com/.
Accommodations for the Disabled
Any person may make a request for a disability-related modification or accommodation needed for that person to be
able to participate in the public meeting by telephoning the Executive Secretary at 714-701-3020, or writing to Yorba
Linda Water District, P.O. Box 309, Yorba Linda, CA 92885-0309. Requests must specify the nature of the disability and
the type of accommodation requested. A telephone number or other contact information should be included so the
District staff may discuss appropriate arrangements. Persons requesting a disability-related accommodation should
make the request with adequate time before the meeting for the District to provide the requested accommodation.
ITEM NO. 2.1
AGENDA REPORT
Meeting Date: September 6, 2012 Budgeted: Yes
Total Budget: $750,000
To: Planning-Engineering- Cost Estimate: $3,303
Operations Committee
Funding Source: All Water Funds
From: Steve Conklin, Acting General Account No: 101-2700
Manager
Job No: J-201108
Presented By: Steve Conklin, Acting General Dept: Engineering
Manager
Reviewed by Legal: N/A
Prepared By: Derek Nguyen, Water Quality CEQA Compliance: Exempt
Engineer
Subject: Approval of Change Orders No. 4 & 5 for Pressure Regulating Stations
Upgrade Project, Phase 1
SUMMARY:
Construction is in progress for the Pressure Regulating Stations Upgrade Project. Submitted for
consideration are Change Orders No. 4 & 5 for one additional work day and $3,303.18 for additional
time, labor and materials for the change in condition for the Jefferson St site.
STAFF RECOMMENDATION:
That the Committee recommend the Board of Directors approve Change Orders No. 4 & 5 for one
additional work day and $3,303.18 to Vido Samarzich, Inc. for construction of the Pressure
Regulating Stations Upgrade Project, Job No. 201108.
DISCUSSION:
In accordance with the contract documents, Vido Samarzich, Inc. submitted Change Orders No. 4 &
5 for changed conditions for the Jefferson Pressure Regulating Station. Proposed Change Orders
No. 4 & 5 request a combined additional one work day required to remove and dispose a 5'x4'x4'
concrete thrust block with rebar and deteriorated 8-inch gate valve.
Additionally, the floor slab of the vault was found to be 14 to 16 inches thick which was significantly
greater than what the record drawings indicated. District staff and its engineering consultant have
reviewed the changed conditions and the time request and recommend approval. Copies of Change
Orders No. 4 & 5 are attached for review and information.
The status of the construction contract with Vido Samarzich is as follows:
. The current contract is $611,924.07 with 141 working days starting June 12, 2012.
• If approved, Change Orders No. 4 & 5 add one work day (0.7% of current contract days) and
$3,303.18 (0.5% of current contract cost) for additional cost.
• If approved, the revised construction contract is $615,227.25 and 142 days.
STRATEGIC PLAN:
SR 3-A: Complete Implementation of Five Year Capital Improvement Plan from FY 2011-2015 with
adopted amendments
PRIOR RELEVANT BOARD ACTION(S):
• On May 10, 2012 the Board of Directors awarded the construction contract in the amount of
$597,020 to Vido Samarzich, Inc. for the construction of the Pressure Regulating Stations
Upgrade, Job No. 2011-08.
• On July 12, 2012 the Board of Directors approved Change Order No. 1 for 27 additional work
days and no additional cost to Vido Samarzich, Inc. for the Construction of the Pressure
Regulating Stations Upgrade, Job No. 2011-08.
• On August 9, 2012 the Board of Directors approved Change Orders No. 2 & 3 for 3 additional
work days and $14,904.07 to Vido Samarzich, Inc. for the Construction of the Pressure
Regulating Stations Upgrade, Job No. 2011-08
ATTACHMENTS:
Description: Type:
C04 C05 Removal of Thrust Block, Valve Floor Slab Jefferson PRS.pdf CO 4&5 Jefferson PRS Backup
Material
YORBA LINDA WATER DISTRICT CHANGE ORDER NO. 4
DATE August 13, 2012
Page 1 Of 1
CONTRACT NAME: Pressure Regulating Stations Upgrade CONTRACTAMT.: 5611 924.0] DAYS: 141
CONTRACTOR: Vido Samarxich, Inc. THIS CHANGE: $2,431.38 DAYS: 0.5
PROJECT NO: 2011-08
OWNER: Yorba Linda Water District REVISED CONTRACT AMT: $614,355.45 DAYS: 141
.5
This Change Omer covers changes to the subject contract as deaonbed herein. The Contractor shall construct, furnish equipment and m materials,
and perform all work as necessary or required to complete the Change Omer items for a lump sum prim agreed upon between tha Contractor
and Yorba Linda Water district otherwise referred to as Owner.
+INCREASE CONTRACT
DESCRIPTION OF CHANGES /OR TIME
+EXTENSIONI
DECREASE IN DR -REDUCTION
CONTRACT (DAYS)
AMOUNT
($)
Van Buren P.R.S.-Remove and dispose of approx. 20 LF of an 18" RCP abandoned $2,431.38 0.5
irrigation line and bulkhead both ends with mortar (line was in conflict w/4' blow off and 8'
vent pipe)
Jefferson P.R.S:Remove and dispose of a 5'X4'X4' concrete thrust block w saber @ N
side of vault between vault and 8' valve and add work required to remove vault floor-14°
16" thick-plan shows approx. W.
NETCHANGE $2,431.38 0.5
REVISED CONTRACT AMOUNT AND TIME $614,355.45 141.5
The amount of the contract will be increased by the sum of $2,431.38 and the contract tlme shall be increased by 0.5 calendar days. The
undersigned Contractor approves the foregoing Change Order as to the changes, 9 any, in the contract prim specified foreac r ram including
any and all supervision rusts and other mis aillaneous costs relating to the change in work, and as to the extension of allowed, if any, for
compietlon of the entire work on account of said Change Order, The Contractor agrees to finish ell labor and materials and perform all other
necessary work. Inclusive of that directly or Indirectly related to me approved time amenelon, required to complete the Change Omer items.
This document cola become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Omer shall be
efedive when approved by the Owner. This Change Omer constitutes full, final, and complete compensation to the Contractor for all costs,
expenses, overhead, level, and any damages of every kind that the Contractor may Incur In connection with the above referenced changes in
the work, Including any impact on the referenced work of any other work under the contract, any changes In the sequences of any wont, any
delay to any work, any disruption of any work, any rescheduling of any work, and any other effect on any of the work under Ihs contract. By
the execution of the Change Omer, the Contractor accepts the contract price change and the contract compimon date change, if any, and
expressly waives any claims for any additional compensation, damages or time extension, in connection with the above-referenced
changes. � t//� //\ ds I
RECOMMENDED: ^^c 5/ s' OWNER DATE: al2.Z1 �1Z
U12-4m,e
ACCEPTED: CONTRACTOR DATE:
114100 ama , Vice ardent
Vido Samarsich, Inv.
APPROVED: OWNER DATE:
Steve Conklin, Ailing General Manager
YORBA LINDA WATER DISTRICT CHANGE ORDER NO. 5
DATE August 14, 2012
Page 1 Of 1
CONTRACT NAME: Pressure Regulating Stations Upgrade CONTRACTAMT.: $614,311 DAYS: 141
.5
CONTRACTOR: Vido Samarsich, Inc. THIS CHANGE: $871.80 DAYS: 0.5
PROJECT NO: 2011-08
OWNER: Yorba Linda Water District REVISED CONTRACT AMT: $615,227.25 DAYS: 142
This Change Order covers changes to the subject contract as described herein. The Contractor shall consinxt, furnish equpment and materials,
and perform all work as necessary or required to complete the Change Order items for a lump sum pnce agreed upon between the Commger
and Yorba Lida Water District othenew usher ed to as Owner.
+INCREASE CONTRACT
DESCRIPTION OF CHANGES f CR TIME
+EXTENSION !
—DECREASE IN DR-REDUCTION
CONTRACT (DAYS)
AMOUNT
l$)
Jefferson P.R.S.-As directed, remove existing Sn valve North of vault. Work included $871.80 0.5
additional excavation, removal of concrete thrust block to North of valve, cut off bolls,
clean flange, remove and deliver A.C.P. riser to district yard, and install new SDR 35 pipe
riser on existing 8" valve for 4°blow off.
NETCHANGE $871.80 0.5
REVISED CONTRACT AMOUNT AND TIME $615,227.26 142
The amount of the contract will bas increased by the sum of $871.80 and the contract time shall be Increased by 0.5 silencer days. The
untlersigned Connector approve$ the foregoing Change Omer as W the changes, if any, in the contract pace specified for each have including
any and all supervision costs and other miscellaneous costa relating W the change in work, and as W the extension of time allowed, if any, for
completion of me entire work on account of said Change Omer. The Connecter agrees to furnish all labor and materials and perform all other
necessary work, Inclusive or mat directly or Indirectly related to the approved time extension, required to complete the Change Omer items.
This document will become a supplement of the contract and all provisions will apply herels. It is understood that the Change Order shall be
effective when approved by me Owner. This Change Omar constitutes full, final, and complete compensation to the Connector for all costs,
expenses, overhead, profit, and any damages of every kind that the Contractor may Incur in connection With the above cleansed changes in
the work, including any impact on the referenced wok of any other work under me contract, any changes in the sequences of any work any
delay to any work, any disruption of any work, any rescheduling of any nark, and any other elect on any of the work under this contract. By
the execution of the Change Omer, the Contractor accepts the contract price change and the contact completion date change, f any, and
expressly waives any claims for any additional compensation, damages or time extensions, In connection with the above-referenced
changes. �J Ti
RECOMMENDED: OWNER DATE: $194;01Z
Derek g e r
ACCEPTED: CONTRACTOR DATE: Z
Mole Samar t, Vic resident
Wtlo S manich, Inc.
APPROVED: OWNER DATE:
Steve Conklin,' Acting General Manager
ITEM NO. 2.2
AGENDA REPORT
Meeting Date: September 6, 2012 Budgeted: Yes
Total Budget: $750,000
To: Planning-Engineering- Cost Estimate: $7,208.91
Operations Committee
Funding Source: All Water Funds
From: Steve Conklin, Acting General Account No: 101-2700
Manager
Job No: J-201108
Presented By: Steve Conklin, Acting General Dept: Engineering
Manager
Reviewed by Legal: N/A
Prepared By: Derek Nguyen, Water Quality CEQA Compliance: Exempt
Engineer
Subject: Approval of Change Order No. 6 for Pressure Regulating Stations Upgrade
Project, Phase 1
SUMMARY:
Construction is in progress for the Pressure Regulating Stations Upgrade Project. Submitted for
consideration is Change Order No. 6 for two additional work days and $7,208.91 for additional time,
labor and materials for the change in condition for the Camino de Bryant site.
STAFF RECOMMENDATION:
That the Committee recommend the Board of Directors approve Change Order No. 6 for two
additional work days and $7,208.91 to Vido Samarzich, Inc. for construction of the Pressure
Regulating Stations Upgrade Project, Job No. 201108.
DISCUSSION:
In accordance with the contract documents, Vido Samarzich, Inc. submitted Change Order No. 6 for
changed conditions for the Camino de Bryant Pressure Regulating Station. Proposed Change Order
No. 6 requests two additional work days required to install fittings on the North and South sides of
the vault to compensate for the 13-inch grade change in elevation on the existing 14-inch main.
The additional work includes excavation for the increased depth of vault, fittings and restraints,
assembly and installation. District staff and its engineering consultant have reviewed the changed
conditions and the time request and recommend approval. Copy Change Order No. 6 is attached for
review and information.
The status of the construction contract with Vido Samarzich is as follows:
. Assuming that Change Orders No. 4 & 5 will be approved, the current contract is $615,227.25
with 142 working days starting June 12, 2012.
• If approved, Change Order No. 6 add two work days (1.4% of current contract days) and
$7,208.91 (1 .2% of current contract cost) for additional cost.
• If approved, the revised construction contract is $622,436.16 and 144 days.
STRATEGIC PLAN:
SR 3-A: Complete Implementation of Five Year Capital Improvement Plan from FY 2011-2015 with
adopted amendments
PRIOR RELEVANT BOARD ACTION(S):
• On May 10, 2012 the Board of Directors awarded the construction contract in the amount of
$597,020 to Vido Samarzich, Inc. for the construction of the Pressure Regulating Stations
Upgrade, Job No. 2011-08.
• On July 12, 2012 the Board of Directors approved Change Order No. 1 for 27 additional work
days and no additional cost to Vido Samarzich, Inc. for the Construction of the Pressure
Regulating Stations Upgrade, Job No. 2011-08.
• On August 9, 2012 the Board of Directors approved Change Orders No. 2 & 3 for 3 additional
work days and $14,904.07 to Vido Samarzich, Inc. for the Construction of the Pressure
Regulating Stations Upgrade, Job No. 2011-08.
ATTACHMENTS:
Description: Type:
C06 13-in grade change Camino de Bryant PRS.pdf C06_13-in grade change_Camino de Bryant Backup Material
YORBA LINDA WATER DISTRICT CHANGE ORDER NO. 6
DATE August 22, 2012
Page 1 Of 1
CONTRACT NAME: Pressure Regulating Stations Upgrade CONTRACT AMT.: $616,227.26 DAYS: 142
CONTRACTOR: Vida Somareich, Ina THIS CHANGE: $7,208.91 DAYS: 2
PROJECT NO: 1011-0 g
OWNER: Yorba Linda Water District REVISED CONTRACT AMT: $622,436.16 DAYS: 144
This Charge Order covers changes to the subject moved as desmbed herein. The Contractor shall consbucq furnish equipment and materials,
and perform all work as necessary Or required le mmplate the Change Order Items for a lump sum price agreed upon between the Contractor
and Yorba Linda Water Dki Whom lse retained to as Owner.
+INCREASE CONTRACT
DESCRIPTION OF CHANGES / OR TIME
+EXTENSION/
- DECREASE IN OR-REDUCTION
CONTRACT (DAYS)
AMOUNT
Camino De Bryant P.R.S.-Install additional finings on the North and South side of vault to $7,208.91 2
compensate for the 13" grade change in elevation on the existing 14' main. Work includes
additional engineering, layout, excavation, export, finings (quote included for fittings and
restraints), assembly, and installation. Work also includes additional excavation for
increased depth of vau8 and piping, including export.
NETCHANGE $7,201 2
REVISED CONTRACT AMOUNT AND TIME $622,436.16 144
The amount of the contract will W increased by the sum of $7.296.91 and the contract time shall be Increased by 2 calendar days. The
undersigned Contractor approves the foregoing Change Order as to the charges, if any, in the contract prim intended for each Hem including
any and all supervision costs and other miscellaneous costs relaft to the change in wort, and as to the extension Of time allowed, if any, for
completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other
necessary work, inclusive of twat tllrecty or indirectly related to the approved time extension, required to complete the Change Ober Items.
This document will become a supplement of the contract and all provisions all apply hereto. It is understood that the Change Order shall be
effective when approved by the Owner. This Change Order constitutes full, final, and complete mmpensation to the Contractor for all bests,
expenses, overhead, profit, and any damages of every kind that the Contractor may incur in connection with the above referenced charges in
the work. Including any impact on the referenced work of any other work under the contract, any changes in the sequences of any wok, any
delay to any work, any disruption of any work, any rescheduling of any wndr, and any other after on any of the wort under this contract. By
the execution of the Charge Order, the Contractor accepts the contract price change and the contract completion date change, 6 arty, and
expressly waives any claims for any additional mmpensatidn, damages or time extensions, in connection with the above-referenced
changes.
RECOMMENDED: OWNER DATE:
Oere r g , Proje er
ACCEPTED: CONTRACTOR DATE: L3
too me , Vi resident
VidaS marsich, Inc.
APPROVED: OWNER DATE:
Steve Conklin, Acting General Manager
ITEM NO. 2.3
AGENDA REPORT
Meeting Date: September 6, 2012 Budgeted: No
Total Budget: $0
To: Planning-Engineering- Cost Estimate: $350,000
Operations Committee
Funding Source: All Water Funds
From: Steve Conklin, Acting General Account No: 101-2701
Manager
Job No: J2012-13
Presented By: Steve Conklin, Acting General Dept: Engineering
Manager
Reviewed by Legal: N/A
Prepared By: Hank Samaripa, Project CEQA Compliance: Exempt
Engineer
Subject: Yorba Linda High School Park Pipeline Relocation
SUMMARY:
The proposed Yorba Linda High School Park, within Placentia Yorba Linda Unified School District's
(PYLUSD) property located south of Yorba Linda High School, includes proposed grading with
nearly 18-feet of fill over our existing 39-inch diameter Bryant Cross Feeder (BCF) pipeline. See
attached figures. The BCF pipeline will be unable to support the additional fill, and must be
relocated. Per the Pre-Annexation Agreement with PYLUSD, the District is responsible for the
design and construction costs for relocating approximately 500 lineal feet of the 39" BCF pipeline.
To meet PYLUSD's proposed construction schedule, District staff is requesting to issue a
Professional Services Agreement (PSA) with Albert Webb Associates, Inc. (Webb Associates) for
engineering services for the relocated BCF pipeline.
STAFF RECOMMENDATION:
That the Committee recommend the Board of Directors authorize execution of a PSA with Webb
Associates in the not-to-exceed amount of$20,700 to provide professional engineering services for
relocation of the 39-inch Bryant Cross Feeder pipeline.
DISCUSSION:
On September 4, 2012, District staff met with the PYLUSD and the City of Yorba Linda (City) to
discuss their proposed Yorba Linda High School Park development (Park). The PYLUSD is the
property owner; they received developer funding for the park improvements, and the City is working
with PYLUSD to assist in the planning of the Park facilities since the City will be responsible for
maintaining the landscaping after the Park is constructed. The PYLUSD and the City stated that this
Park will include the only regional youth baseball and softball facilities with lighting, and the
residents and youth leagues requested that the oft-delayed Park be constructed ASAP. To
accommodate this goal, the District was requested to expedite the BCF pipeline relocation. Per the
Pre-Annexation Agreement with PYLUSD, the District is responsible for the design and construction
costs of relocating approximately 500 lineal feet of the 39" BCF pipeline. Based on earlier
discussions with PYLUSD that this project may be necessary, District staff solicited proposals from
three design firms. The three firms submitted proposals.
Results of the ranking by the District's review team and fees are as follows:
Firm Evaluation Ranking Proposed Fee
Webb Associates 1 $20,700
Lee & Ro 2 $26,465
MCE 3 $17,500
Based on the above, staff recommends award to Webb Associates. This firm had the best proposal,
the most responsive schedule, best project team and experience, and proposed fee and staff hours
which were reasonable and appropriate based on the scope of work.
Note that this project was not included in the Board approved 2012-13 CIP. However, funds are
available, though ear-marked for other potential projects. Staff will consider the impact of this as
part of the budget process for FY 13-14 and provide recommendations for the Board's
consideration.
STRATEGIC PLAN:
SR 3-A: Complete Implementation of Five Year Capital Improvement Plan from FY 2011-2015 with
adopted amendments
PRIOR RELEVANT BOARD ACTION(S):
On June 28, 2008, the Board of Directors signed the Pre-Annexation Agreement with PYLUSD for
the full development of the new Yorba Linda High School and Joint Use Park with the City.
BASTANCHURY ROAD
s o
O �! o
MITI
= vo N
i
1 1 �
�i
RBA LINDA`HIGH SCHOOL SITE
s
2 O
Fo I A
o - o
�O AVENIDA DEL REY
PROPOSED YORBA LINDA HIGH QP��
SCHOOLPARK
N
1,'SCALE
LOCATION MAP
r
i
i
O i
i
f 4 j
i
PROPOSED 39"ST E WATER Al
® APPROX. 540 FEE O PIPE
P O ED20F T
o A EASEM T
ADDED
J
I
o�y
a �
._ /� YHd3 4r ADDED MWL
O/ C3�y �GpJ
y�P�/% �a�oQ•
ADDED WALL ADDED WALL a vim NUMER OF RIM �0�
EX. 39"STL YORBA LINDA
COUNTY WATER DISTRICT
/ PROPOSED P.O.C.
--------------- ------------------------ - - - ----■-■ --------..■ ------ ---- - -------- s -----------
■■■■■■■■■■....■....■....-....-.................................I....c.....................................I ....... Eno NI -- ---- --------�--
�O
■ �■1 ■Y..■■ ■ ■ ' ■ H■_H■_H■_ ■_ � H ..■■■■Htl■H�M ��
s
......----------------------------------------------------------------------...---------—------------------
.... •�•_.�s �s
..y`._R.�.."•�. .rte �. • -�.�. - ----
.
10•W■Z m c.am \EX. 12 STL YORBA LINDA
TO Cfff OF YORBA U�
PER 7RAff NM 7446 O
COUNTY WATER DISTRICT
N (ABANDONED) �i 19
D t5 'I 14
0' r
PORTION WATER I TO B ELOCAT�D
I `(
D7
x
� !
Ld
o LANE_ �I s PROPOSED SEWER
MALAGA __- - A LATERAL
0 -- j z
! 1
? z
o II
c'
o
w N � E O� /
Ld
I �P�
o �• pfd p /
a
o
W LO
10 an UK so VOW IW WW
10 MY
PER nacr ED.sue
x
W
cn
.*
SCALE: 1 " = 60'
x /..
w
APPROVED BY YORBA LINDA WATER DISTRICT PROJECT NO.
x
w % '� REVISIONS ENGINEERING
NO. DATE INITIAL DESCRIPTION APPROVED MANAGER 201213
PROPOSED WATER IMPROVEMENTS
DATE FOR
Q
09/2012 YORBA LINDA HIGH SCHOOL PARK
i ` �� SHEET 1.1
ITEM NO. 3.1
AGENDA REPORT
Meeting Date: September 6, 2012
To: Planning-Engineering-
Operations Committee
From: Steve Conklin, Acting General
Manager
Presented By: Steve Conklin, Acting General Dept: Finance
Manager
Prepared By: Stephen Parker, Finance
Manager
Subject: Status of Meter Program
SUMMARY:
At the August 2012 meeting, the PEO Committee requested that staff provide a report on the status
of water meters in the District; i.e., how many with electronic vs manual read, and the plan for the
future. A copy of the report prepared by staff is attached for discussion.
ATTACHMENTS:
Name: Description: Type:
Meter Reading Section status v2.docx Status of Meter Program Backup Material
STATUS OF METER PROGRAM
• Background
• In adopting the FY2005/2007 budget, the Board approved the first phase of
transition to radio-read meters at a budget of$2.8 million. In the FY 2007/2009
budget, an additional $1,000,000 was budgeted.
• In the years 2005 through 2008, approximately 7,973 meters were installed and
approximately 4,030 radio-read transmitters were placed on existing Sensus
meters. Combined with newly annexed and developed areas, the District had
over 13,900 radio-read meters.
• Since then, approximately 1,400 more meters have been installed due to
failures, and replacements continue to be installed at approximately 300 per
yea r.
• In April/May of 2009, as a result of increased efficiency, monthly reading was put
into place.
• The Meter Reading section was also given more responsibilities than previously—
taking a look at unusual usage and going to the field to investigate and leave a
note for the customer regarding the usage, interacting with customers regarding
high-bill complaints and creating accounts in utility billing system for new meter
sets and backflows.
• In September 2010, the Finance Director was requested to work on completing
the project to have all meters be radio-read meters.
• In April 2011 an RFP went out to four chosen vendors. The results were
evaluated in May 2011 by a committee of employees from Accounting, Customer
Service, Meter Reading and Operations. It was determined the cost would be
approximately$2.5 million for conversion of remaining meters to radio-read
technology.
• The GM decided not to proceed with presenting the cost to the Board with the
reasoning that the District did not have enough evidence of water loss to move
forward with a $2.5 million capital project. The GM did approve moving forward
with recommended vendor for meter replacements in the eastern service area.
• Current situation
0 63% of the District is equipped with radio-read meters (15,386) in routes that are
read strictly by vehicle units.
0 6% of the District is equipped with radio-read meters (1,564) in routes that are
manually read.
0 31% of the District is equipped with direct-read meters (7,500) in routes that are
manually read.
o In May, 2011, during a vacancy, the 5t" meter-reading position was not filled so
as to consider if the position was necessary.
o Without the fifth position, the Meter Reading section fell behind on service
orders, shop maintenance and troubleshooting.
o Due to the backlog, meter replacements and meter maintenance began being
outsourced to Operations Department in the fall of 2011. This has resulted in
some inefficiencies.
• Potential Options for the future
• Status quo— replace direct-read meters with radio as they fail.
• Complete radio reading throughout District
• Consider AMI technology (which allows reads to be sent via radio waves and
received by a collector).
ITEM NO. 3.2.
YLWD SOURCE WATER SUMMARY
FY 2012-13
IN-LIEU ACTUAL ADJUSTED TOTAL MONTHLY YTD BUDGET
GW GW IMPORT DEMAND GW GW (Demand Est.) DELTA
MONTH (AF) (AF) (AF) (AF) (%) (%) (AF) (%)
Jul-12 785.3 1,622.6 2,407.8 32.6% 32.6% 2,354.0 2.3%
Aug-12 793.7 1,706.4 2,500.1 31.7% 32.2% 2,316.0 7.9%
Sep-12 2,032.0
Oct-12 1,714.0
Nov-12 1,354.0
Dec-12 1,218.0
Jan-13 1,062.0
Feb-13 1,016.0
Mar-13 1,204.0
Apr-13 11 506.0
May-13 1,992.0
Jun-13 2,232.0
FYTD - 1,578.9 3,329.0 4,907.9 32.2% 1 4,670.0 1 5.1%
Red denotes In-Lieu month
Allowable GW(YTD) 2,469.7 (AF)
Underpumped 890.7 (AF)
GROUNDWATER PERCENTAGE
80.0%
'MONTHLY GW(%)
75.0%
_�_YTD GW(%)
70.0% ®BPP GOAL 50.3%
65.0%
60.0%
55.0%
50.0%
45.0%
40.0%
35.0%
30.0%
Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
Month
WATER SUPPLY
FY 2012-13
August 2012 Water Supply
IN-LIEU GW
0.0%
GW
32.6%
IMPORT
67.4%
2012-13 YTD Water Supply
GW
32.2%
IMPORT
67.8% GW BPP GOAL
50.3%
TOTAL WATER USE
FY 2012-13
2'600
77.7 Monthly Average Mean Temperature(0 F) 010-11 GW 010-11 IMPORT
73.071.4 72.9 ■11-12GW ■11-12 IMPORT
2'400 9.7 73.2 ■12-13 GW 012-13 IMPORT
2,200 67.8
70.8 70.3
66.4
2,000
63.8 65.3
1,800 —
66.4
1,600 —
62.4
Li
Q 1,400 —
d 65.4 61.5 55.5 59.7 58.0 62.0
59.6 57.6
c 1,200
60. 55.2
58.7
1,000
56.4
800
600
400 — — - —
200 —
0
NQ) NN N"� NI �� NIV NIZ, NN NrrV NI �� 0 N� NN 0 N� �� 0 �� �rV.`b �N �ti �rb NN �ti�rb NN N,V N,b NN �I �rb .� �rV.16
JC J�
Al o�'
Al 0"a"a,
PPP 5 5 5 O O O > > > a
Month
FY 2012-13 YTD Water Supply
22,000 Budgeted Total GW+ Import
-me—Actual Total GW+ Import
20,000 mmmw—BPP GW Goal 50.3% 04
Actual GW Production
1$,000 Actual Total GW+ Import 2011-12
16,000
14,000
U-
Q
12,000
E
10,000
8,000
6,000
4,000
2,000
0
Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
Month
ITEM NO. 3.3.
Monthly Production Summary Report
August 29,2012
Water Production Out of Service Equipment
•Groundwater 31.5 Equipment Name Reason for Out of Service
• Import Water 68.5 Well 11,20 Control and Testing Issues; Request from OCWD
Max Day 28.5 Timber Ridge Booster#1 Pump locked up
Min Day 22.1 Well 18 Gas Engine Head Replacement Scheduled PM
Average Day 25.5 Oc-66 Water Main Break
Weather Conditions
Max Temperature 99
Min Temperature 77
#of High Wind Days 0 Returned to Service
#of Red Flag Days 0 Equipment Name Date
Inches of Rain 0 Richfield C12 system 8/17/2012
Water Quality Well 18 8/16/2012
Location Average Cl2 Dose Oc-66 8/27/2012
Richfield (North Loop) 1.40
Richfield (South Loop) 1.30
Lakeview Booster (Zone 2) Off Line After Hours Responses
Lakeview Booster (Zone 3) Off Line Hi/Lo Water Levels 17 Related to work on Rich. C12 System
Well # 15 Off Line Hi/Lo C12 Levels 2
Well #20 Off Line Communication Alarms 6
Location Average Cl2 Residual Pump Alarms 2
Highland Booster 1.25
Valley View Booster 2.50
Paso Fino Booster 2.50
Hidden Hills Reservoir 1.70
Camino de Bryant Reservoir j 1.50
* Still working on start up for Well #20 this month, having problems with controls. * 8/7/12 earthquake 4.5 * 8/8/12 earthquake 4.5 * 8/29
earthquake 4.1. * 8/25 Large water leak on 8" line, requiring a shutdown of OC-66 for 24 hours.
PREVENTATIVE AND REACTIVE MAINTENANCE ITEM NO.3.4.
FISCAL 2012/13
Fiscal 2012-13 JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN
Percent of target 8% 25% 33% 42% 50% 58% 67% 75% 83% 92% 100%
HYDRANTS(3,881) Target;all hydrants to be serviced annually.
INSPECTED THIS MONTH 361 67
INSPECTED THIS YEAR 361 428
OF TOTAL 9.3
VALVES(10,706/2=5,353) Target;all valves to be operated every two years
OPERATED THIS MONTH 486 496
OPERATED THIS YEAR 4861 982
OF TOTAL 9.1%1 L-s Ye
DEAD ENDS(155 X 2=310) Target;all dead ends to be flushed twice each year.
FLUSHED THIS MONTH 01 1
FLUSHED THIS YEAR 01 1
OF TOTAL 0.0%
AIR VACS(330) Target;all air/vacs to be serviced annually.
INSPECTED THIS MONTH 0 249
INSPECTED THIS YEAR 0 249
OF TOTAL 0.0
PRVs(150 x 2 per Yr=300) Target;all PRVs to be serviced biannually.
INSPECTED THIS MONTH 41 5
INSPECTED THIS YEAR 41 9
OF TOTAL 1.3
WATER LEAKS Target;all leaks repaired at first available opportunity.
MAIN REPAIRED 1 2
SERVICE REPAIRED 4 1
SERVICE REPLACED 11 11
AMS REPLACED 6 10
METERS Target;all meter work completed no later than next working day.
NEW INSTALL 1 6 1 5
STUCKS 1 41 0
SEWER CLEANING(235 M) Target;all sewers to be cleaned annually.
CLEANED THIS MONTH 25.72 20.06
CLEANED THIS YEAR 25.721 45.78
%OFTOTAL 10.94%1 1948r ,o
SEWER TELEVISING(39.17M) Target;all sewers to be televised every 6 years.
TELEVISED THIS MONTH 3.75 4.03
TELEVISED THIS YEAR 3.75 7.78
OF TOTAL 9.57%
OTHER SEWER WORK.
S.S.OVERFLOWS 0 0
SERVICE CALLS 0 2
ROOT CONTROL 0 6,316
REHAB FOOTAGE 15 482
MAIN REPAIRS 1 2
MANHOLE ROOT CLEANING 2 0
MANHOLE REPAIRS 1 31 3
ITEM NO. 3.5
AGENDA REPORT
Meeting Date: September 6, 2012
To: Planning-Engineering-
Operations Committee
From: Steve Conklin, Acting General
Manager
Presented By: Steve Conklin, Acting General Dept: Operations
Manager
Prepared By: Steve Conklin, Acting General CEQA Compliance: Exempt
Manager
Subject: Chlorine System Project Status Report
SUMMARY:
In July 2012, the PEO Committee recommended and the Board approved proceeding with a
contract for replacement of the computer-based control system for the chlorine generation system
for disinfection of well water. The PEO Committee requested a report back on the work and final
cost after completion. That work has been completed and a staff memo is attached with the
requested information for review and discussion.
ATTACHMENTS:
Description: Type:
Memo Richfield Chemical System PLC Upgrade.docx Chlorine System Project Status Report Backup Material
ElYorba Linda
Water District
Memo
To: Steve Conklin
Date: August 27, 2012
From: Rick Walkemeyer
Subject: Chlorine System Project
Summary
On July 5, 2012,the PEO Committee reviewed and considered this item, and asked that a report
be made to PEO after completion of the work. The Board approved proceeding with the work by
Severn Trent on July 12, 2012, and the work was recently completed. This memo is a report to
PEO on the background and final cost of the work.
The chlorine disinfection system operating in the Richfield Yard produces and doses sodium
hypochlorite disinfectant for the groundwater pumped from the wells on site. The system was
completed in 2000. The computer components that run the system are failing and replacement
parts can no longer be purchased. The District and the system manufacturer, Severn Trent,
inspected and tested the generation system hardware and determined that it was in very good
condition. It was thus determined to keep the hardware and replace the computer-based control
system with all new elements.
The original cost quote for the replacement work was $18,400 plus travel expenses for the
programmer/installer. The final cost, after additional work for rewiring,was $25045.44•
Background and cost information are provided below.
Background
In 2000 the District constructed a plant on the Richfield site to manufacture sodium
hypochlorite("chlorine")to disinfect all the ground water pumped from wells on the site. The
plant consisted of three CT-300 ClorTec systems that are each run by their own individual
control panel and a Rapid Rectifier. Each of the three individual control panels is run to a
master control panel.All of the four control panels were run by a Modicon Compact 984-258
PLC for which replacement parts is no longer available. Each CT-300 system has its own rack
with its own cells and rectifier. The master control panel turns on each CT-300 system as
needed, interfaces with the Districts SCADA system, and controls the metering pump systems.
The Modicon Compact line of PLC was used in the industry for 35 years. Due to the use of lead
in the circuit boards it was removed from sale about 5 or 6 years ago. We have a stock of some
new parts and more used parts but the required modules were not in our inventory. The
software called"Concept" used for the compact PLCs is being phased out. It will no longer be
fully supported and will not be upgraded to support newer operating systems like Windows 7.
The modules noted above that were failing were used to read high resolution analog inputs, such
as rectifier volts, amperage,flows and levels used for the system controls. Each CT-300 system
had two of these cards. Without these inputs the units fail and shut down, cutting the capacity
by one-third,which is inadequate for groundwater pumping during summer demands. These
PLCs have been running for 12 years,well past their expected life.
The currently speed PLC is the Modicon model M340 which has been installed in ten District
locations over the last few years including the Hidden Hills Reservoir, Highland Booster Station,
and the new Well 20. The programing software for the M340 is called"Unity." The M34o has
proven to be a robust, reliable, and full featured PLC.
Conversion Work
Work to program and wire the new PLCs started Wednesday July 18 and completed on August
17th. No work was done the week of August Stn. The program conversion worked and was
successful in saving a lot of time,but the rewiring took almost twice the estimated time.
Communication to the old Master PLC was tried without success. Resolving this communication
issue caused some delay in the project. It was decided to just move forward with upgrading the
master as communications between the new PLCs worked. Once the master PLC was rewired
and programed, communication to the other PLCs was quickly established.Thereafter the
system was successfully integrated into the District's SCADA system and extensively tested and
validated.
Additional work on the performance of the chlorine loops, requested by the Chief Plant
Operator,was addressed. The programmer did more loop tuning and exposed more control
adjustments to help improve these loops.
Cost
On July 12, 2012 the Board of Directors approved work with an estimated cost for labor on a
time-and-materials basis of$18,400 plus staff travel expenses. The work by Severn Trent
included the programing,testing, adjustments, and validation of the program with the new
Model M340 PLCs using the new M340 Unity programing software. The estimated time was
loo hours labor plus expenses for transportation,food&lodging.
Additionally,the scope was expanded to add the necessary rewiring of the panels to the new
PLC's and to address a long term dosing loop control problem. These critical loops control the
amount of chlorine metered into the system.
The total billing from Severn Trent is summarized below:
Original Quote with loo Hrs.labor(time&materials based)
$18,400.00
Additional work(not in Quote) 12 Hours. $1,800.00
Expenses (transportation,food&lodging) $ 4,845.44
Total $25045.44
The original quote was $18,400.00 plus travel expenses. The final cost was $25,045.44,Which
included added work for rewiring the panels.
In summary the life of the disinfection equipment has been extended in a very cost effective way.
The four PLCs were replaced and are now working allowing our Operators to make the critical
chlorine needed to keep our system safe and reliable.
ITEM NO. 3.6
AGENDA REPORT
Meeting Date: September 6, 2012
Subject: Groundwater Producers Meeting Report
ATTACHMENTS:
Description: Type:
GWP Mtq Notes 8Aug2012.docx GWP Meeting Report for August 2012 Backup Material
ImYorba Linda
Water District ,
MEMORANDUM
DATE: August 8, 2012
TO: Steve Conklin
FROM: John DeCriscio
SUBJECT: Groundwater Producers Meeting, August 8, 2012
1 attended the Groundwater Producers (GWP) meeting on August 8, 2012 at OCWD
Field Headquarters. A summary of each item discussed is as follows:
1. Carbon Footprint Workshop. Assembly Bill 32 (Global Warming Solutions Act)
passed in 2006. The goal of this bill is to reduce by the year 2050 the "carbon
footprint" back to what it was in 1990. It is estimated that water-related energy
use makes up approximately 5% of the total greenhouse gas emissions,
(GHGE). In order to establish a baseline 1990 and our current carbon footprint, a
planned three-phase approach has been developed, which will require
information from water purveyors in the near future.
• Phase 1: Research and data collection, inventory of GHGE sources. This
phase is expected to be completed by summer 2012
• Phase 2: Data Evaluation and Model Development. This phase is
expected to be completed by winter 2012.
• Phase 3: Modeling and Deliverables. This phase is expected to be
completed in fall 2013.
Yorba Linda Water District will be requested to provide staff time to collect this
data and get the information back through OCWD to the program manager in a
very short time period.
2. Maintaining a constant BPP concept. OCWD is considering a refined
approach to managing the groundwater basin. In the current approach OCWD
establishes a Basin Production Percentage (BPP) on an annual basis and then
operates the basin to that production rate throughout that year to manage the
accumulated overdraft.
1
Historically the BPP has averaged 70.9%, which may be the percentage OCWD
staff is most comfortable working towards for a constant pumping rate. However
there are several issues to consider before establishing a constant BPP:
• The BPP is the District's main means for managing the groundwater basin
and they don't want to be politically "locked" into a set BPP.
• There is a concern that if/when the basin gets down to a critical level and
there isn't any recharge water available, how to respond.
• No one is completely sure of each of the Producers' pumping capacity and
if most Producers could even benefit from a higher constant BPP.
In the new approach to be studied for potential implementation, there are several
possible benefits that have been identified:
• Easier operations for the Groundwater Producers
• Reduced water supply cost
• Greater supply reliability
• Easier planning for the Producers
• It maximizes the utility of the groundwater basin
The OCWD Board has requested staff to put together a committee to gather
information and study potential ways to manage the basin with a constant BPP.
This committee will meet regularly and report to the Board.
3. Annexation Update. OCWD staff is looking to take to their Board a
recommendation to move forward with the YLWD/IRWD/Anaheim annexations.
Mike Markus addressed the Producers and told them that OCWD staff feels the
annexations are in compliance with the District Act and, therefore, should move
forward for a vote by OCWD's Board.
There was a recommendation by several Groundwater Producers to form a
committee outside of the Producers meeting to discuss the proposed
Annexations and impacts. The first meeting of the committee will follow next
month's Groundwater Producers meeting and YLWD will have staff participating.
4. Update of Field Headquarters activities. OCWD's Conrock and Warner basins
are being drained and cleaned this summer. After cleaning, the plan is to leave
the basins low in order for them to be available to collect winter storm flows. In
the meantime the fishing concession has been moved to Anaheim Lake and will
remain there throughout the summer.
2
ITEM NO. 3.7
AGENDA REPORT
Meeting Date: September 6, 2012
Subject: Status Report on Capital Projects in Progress
ATTACHMENTS:
Description: Type:
CIP Rept Sept20l2.pdf Status Report on Capital Projects in Progress Backup Material
CAPITAL IMPROVEMENT PROJECTS STATUS REPORT
Date: Sept 1, 2012
New Information since Last Report is Shown in Red
IN CONSTRUCTION
Project Current Status Next Actions Comments
1 Highland Booster Station Upgrade District attained"Beneficial Recommend filing Notice
Budget: $5,000,000 Job No. 200814 Use." Contractor completing of Completion at 9/13/12
Project Contact: Joe Polimino punch-list items. Board meeting.
Planned Completion Date: August 2012
2 Well 20 Equipping The project has been completed. Recommend filing Notice
Budget: $1,200,000 Job No. 200711 of Completion at 9/13/12
Project Contact: Joe Polimino Board meeting.
Planned Completion Date: August 2012
3 Green Crest Lift Station Upgrades Awaiting repair of valve vault Issue Notice of Close the job and update record
Budget: $100,000 Job No. 201116S access hatch. All other new Completion and file with drawings.
Project Contact: Hank Samaripa equipment completed and County Recorder.
Planned Completion Date: July 2012 operational.
4 Fairmont Reservoir Valve Replacement Inlet check valves not working Replace inlet valves Staff, assisted by Counsel,
Budget: $210,000 Job No. 201011 correctly; staff working with during fall or winter 2012 submitted August 2012 letter to
Project Contract: Derek Nguyen Contractor for replacement when demands are lower. Contractor requesting valve
Planned Completion: May 2012 replacement.
5 Yorba Linda Blvd. Pipeline Contractor continues installing Contractor to finish Contractor placed four electronic
Budget: $1.6M Job No. 2008-17 pipe from Ohio St., east. Began potholing, then trench and message boards through-out site,
Project Contact: Joe Polimino potholing at pipe crossing shore pipeline crossing at updating the public daily of
Planned Completion Date: November 2012 future pump station site. Gun Club Rd. current construction operations.
6 Pressure Regulating Stations Upgrade Van Buren & Jefferson sites are Expected completion date The next and final upgrade is
Budget: $1,000,000 Job No.: 201108 completed. Contractor is for Camino de Bryant is Timber Ridge. Expected
Project Contact: Derek Nguyen working on Camino de Bryant Sept 21, 2012. construction completion in
Planned Completion: October 2012 site. December 2012.
1
CAPITAL IMPROVEMENT PROJECTS STATUS REPORT
Date: Sept 1, 2012
New Information since Last Report is Shown in Red
IN DESIGN
Project Current Status Next Actions Comments
1 Lakeview Grade Separation (OCTA Project) Negotiating OCTA cost After cost-sharing is Awaiting final cost sharing
Budget: $700,000 Job No. 201002 sharing. resolved, staff to receive and decision and design submittal
Project Contact: Anthony Manzano approve final design. from OCTA's consultant.
Planned Completion Date: Late 2013
2 2010 Waterline Repl.,Ph.II.: Tamarisk,Hidden Contract documents October 18, 2012 bid due Construction expected to start
Hills,Catalina Ct., Gordon Ln. &Richfield Rd. finalized and advertised date. January 2013, with Richfield
Budget: $13M Job No. 201120 (posted on Planwell). Road work starting first.
Project Contact: Anthony Manzano
Planned Completion Date: Late 2013
3 Yorba Linda Blvd. Pump Station Final plans and specs Advertise on October 1, Projected start of construction is
Budget: $2.3M Job No. 200817B signed and ready for 2012. Bids due November 8, January 2013.
Project Contact: Hank Samaripa advertising. 2012. Award to follow.
Planned Completion Date: Dec 2013
2
CAPITAL IMPROVEMENT PROJECTS STATUS REPORT
Date: Sept 1, 2012
New Information since Last Report is Shown in Red
IN PLANNING
Project Current Status Next Actions Comments
1 Northeast Area Planning Study PSA executed, kick-off mtg. Site visit with Carollo and Anticipating January 2013
Budget: $120,000 Job No. 201011B completed and Carollo review of initial model completion of NE Area
Project Contact: Anthony Manzano Engineers, Inc. (Carollo) started calibration. Planning Study
Planned Completion Date: January 2013 work.
2 Fairmont BPS & Site Improvements Prepare conceptual site plan, to Prepare draft RFP for Northeast Area Planning
Budget: $6,000,000 Job No. 201011B be part Fairmont BPS upgrade Engineering, Design, and Study and hydraulic
Project Contact: Hank Samaripa RFP. Construction Services. analysis will provide key
Planned Completion Date: Jan 2014/15 data.
3 Well 21 Project Continuing to work with OCWD Review lease and easement Will begin preparation of
Budget: $2,300,000 Job No. 200922#21 staff on agreement conditions costs with YLWD Board. If license agreement with
Project Contact: Anthony Manzano and proposed cost of lease and approved, will submit RFP OCWD for access and
Planned Completion Date: TBD easement areas. for well-drilling consultant. drilling of well.
4 YL High School Park Pipe Relocation Working with City of YL to Execute PSA w/Consultant City of YL proposes to
Budget: $350,000 Job No.: 201213 relocate 39" Bryant Cross Feeder for pipeline relocation design begin grading work
Project Contact: Hank Samaripa Pipe out of proposed fill area. and coordinate const. work. January to February, 2013
Planned Completion Date: December 2013
3
ITEM NO. 3.8
AGENDA REPORT
Meeting Date: September 6, 2012
Subject: Status of Strategic Plan Initiatives
ATTACHMENTS:
Description: Type:
Strat PI Tracking- August20l2.xlsx Strategic Plan Tracking Sep 2012 Backup Material
Strategic Plan Initiatives Status Report
Planning-Engineering-Operations Committee
Strategies Start Date Completion Lead Party August 2012 Progress
Date
FR 2: Increase Reserve Funding
Analyze the Asset Annual Review Completed construction of upgrades to
Management Plan to Prior to Budget Engineering
FR 2-B Determine Future Dec-11 and CIP Manager Greencrest Sewer Lift Station. Preparing
GIS database for eastside sewers.
Needs Update
SR 1: Work Toward Service Reliabilitv and Efficiency
Service Demand Projections were examined
SR 1-13 Forecast Service Oct-10 Jun-11 Engineering and incorporated into the District's 2010
Demand Projections Manager Urban Water Management Plan (dated May
2011) out to Year 2035
OCWD responded on Aug 22 with proposed
Develop Additional Engineering cost data. Internally discussed with EAO
SR 1-E Well Sites Mar-11 Jun-12 Manager on Aug 22 and PEO on Sep 6. Preparing
response to OCWD for agreement terms.
SR 3: Continue Implementation of Ca itaI Improvement Project Plan 2007-2012
Complete
Implementation of
Five-Year Capital Current status is approximately $8.7
SR 3-A Improvement Plan On-going On-going Engineering million of projects in construction phase
from FY 2007-2012 Manager and $18.3 million in the planning and
design phases.
with Adopted
Amendments
Conducted kickoff mtg on Aug 9 with
Continue Planning for Carollo Engineers for prep of Northeast
Long-Term Capital Engineering Area Planning Study. Responded to
SR 3-B Improvements and On-going On-going Manager County for Cielo Vista EIR preparation.
Replacements Attended community mtg for YL Estates
Project.