HomeMy WebLinkAbout2012-10-04 - Planning-Engineering-Operations Committee Meeting Minutes MINUTES OF THE
YORBA LINDA WATER DISTRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
October 4, 2012
A meeting of the Planning-Engineering-Operations Committee was called to order by
Director Collett at 3:00 p.m. The meeting was held at the District's Administrative Office
at 1717 E Miraloma Ave, Placentia CA 92870.
COMMITTEE STAFF
Director Ric Collett, Chair Steve Conklin, Acting General Manager
Director Robert R. Kiley Lee Cory, Operations Manager
Stephen Parker, Finance Manager
John DeCriscio, Chief Plant Operator
Mike Kiddie, Senior Fleet Mechanic
Jennifer Hill, Meter Services Lead
After Director Collett opened the meeting, Mr. Conklin requested that an item, Payment
for AQMD Violation for Late Submittal, be added to the agenda, as this issue came up
after the posting of the agenda, and is an issue that the Committee needs to review and
consider at its October 2012 meeting due to the need to respond to AQMD. The
Committee voted to add this to the agenda as Item 2.3.
1. PUBLIC COMMENTS
None.
2. ACTION CALENDAR
2.1. Approval of Change Orders No. 7-10 for Pressure Regulating Stations
Upgrade Project, Phase 1
Mr. Conklin reported that work is progressing on the project, with three
sites complete and work beginning at Timber Ridge, the fourth site. He
noted that extra work was required at the Camino de Bryant site that was
not part of the original project. The extra work was presented and
discussed as proposed change orders no. 7 through 10. Following
discussion, the Committee supported the staff recommendation that the
Board approve payment of Change Orders No. 7 thru 10 for one-half
additional work day and $2,820.33 added cost.
2.2. Amendment No. 4 to MWH Americas Professional Services Agreement —
Construction Support Services for the Highland Booster Pump Station
Replacement
Mr. Conklin recalled that the Board approved the Notice of Completion in
September 2012 for the Highland BPS Project and that the station is
working well. He noted that the District's engineering consultant on the
project, MWH Americas, had a Professional Services Agreement to
provide construction support services based upon a project completion
1
date of March 2012. However, while the District was able to begin using
the facility to deliver water, final completion of the project was not
achieved until September 2012, six months later than anticipated. During
the last six months, MWH continued to provide construction support
services to the District, including contractor coordination, scheduling and
sub-consultant management. These out-of-scope services provided by
MWH were reviewed and discussed with the Committee. Following
discussion, the Committee supported the staff recommendation that the
Board approve Amendment No. 4 for MWH in the amount of $9,998 for
additional support services for the subject project.
2.3. Payment for AQMD Violation for Late Submittal
Mr. Cory reported that a Notice of Violation was received from the South
Coast Air Quality Management District (AQMD) on October 1, 2012,
because the District did not submit emission tests to AQMD until after their
due date. He noted that there was no emissions violation. The violations
are for late submittal of the test results for which a penalty payment of
$3,300 is requested from AQMD. Mr. Cory and Mr. Kiddie discussed
AQMD's required testing program for natural-gas powered engines. Mr.
Kiddie reviewed the situation that lead to the late submittal of test results
as well as the plan to meet submittal deadlines for the future. It was noted
that the violation letter called for payment by October 11, 2012, and that
Mr. Kiddie placed a call to AQMD requesting a time extension to respond.
After discussion, the Committee supported the staff recommendation to
proceed with processing of a check for $3,300 to settle the violation. Mr.
Kiddie left the meeting at the completion of this item.
3. DISCUSSION ITEMS
3.1. Meter Testing Update
Mr. Parker and Ms. Hill provided a status report on the District's water
meter program at the September 2012 PEO Committee meeting and
provided a response today to questions asked in September. Items noted
included:
• After investigating the potential for outsourcing testing of meters, it
does not appear to be a viable or cost-effective option.
• After contacting six other water providers in the area, none were
interested in a reciprocal meter cross-testing arrangement.
• Two local providers, IRWD and MNWD, invited YLWD staff to visit
their meter testing facilities and see testing methods.
• Discussed the potential costs and benefits and reasonable timeline
for the change-out of meters on the east side to radio-read units.
• Discussed the existing customers (relatively few) that tend to have
high water demands that are above the top-end rated capacity of
their meters. Under this condition, over time, the meters are
overtaxed, may under register, and may require replacement
sooner than specified by the manufacturer.
2
Following discussion on the above, the Committee asked staff to
investigate the following and provide feedback to the Committee:
• Further investigate and determine the estimated ROI (return-on-
investment) for change-out of the east side meters.
• Report on visits to meter testing facilities at IRWD and MNWD.
• Report on cost and viability of building and equipping a bench and
system for in-house testing of meters.
• Concerning the issue of customers who operate meters with
demands that typically exceed the high-end specifications, return
with ideas for discussion for a potential policy on testing of meters,
and for the required upsizing of meters, if use is out of spec over a
given time frame.
3.2. Highland Reservoir Ingress/Egress Easement
Mr. Conklin reported that representatives for a potential residential
development of a 5-acre undeveloped parcel at 5225 Highland Avenue
met with District staff to determine if the District might be amenable to
granting an ingress/egress easement for the land-locked parcel. He noted
that staff performed a preliminary investigation and found no reason not to
further pursue the granting of the easement along the northerly edge of
the District's Highland Reservoir site. Mr. Conklin also reported that the
representatives indicated a willingness to purchase a 5,000 SF easement
at a fair-market value of $22.50/SF, for a total cost of $112,500. Following
discussion, the Committee asked staff to proceed, working with the
representatives and the developer (upon payment of District-required
Development Fees), on documents necessary for the easement, and
water and sewer service for the potential residential development, and to
advise the Committee as the project advances.
3.3. Monthly Groundwater Production and Purchased Import Water Report.
Mr. DeCriscio reported that water demand in September was 14% over
the projected demand, and that cumulatively for July through September,
demand is 7.9% over that projected. He noted that groundwater has been
32% of our supply and that we are making the changes to ramp up our
use of groundwater to achieve our goal of 50.3% of our total demand by
June 30, 2013.
3.4. Monthly Preventative Maintenance (PM) Report.
Mr. Cory reported on the status of PM and Reactive Maintenance through
September. He noted that our crews were concentrating on PM on valves
and air vacs, and will now transition to other work items to bring those up
to target levels. He discussed sewer cleaning and televising of the east
side sewers that the District took over in July 2011, and advised that our
crews have cleaned all of these sewers and addressed problem areas. In
the process, the crews cleaned and maintained sewers and manholes that
have not been cleaned in several years. Mr. Conklin noted that Lee Cory,
Diane Dalton and Ariel Bacani made a presentation to the Sept CAC
3
Meeting on the District's sewer system and the work required to maintain
it. Mr. Conklin commented that the CAC presentation was well received,
with an extensive discussion.
3.5. Monthly Production Division Report
Mr. DeCriscio reported on the above for September, noting that the max
temperature for the month was 108 deg F and the max water-use day was
28.3 million gallons. He reported on water quality parameters, equipment
removed from service and returned to service, PMs performed on major
equipment and facilities and after-hour responses.
3.6. Groundwater Producers Meeting Report
Mr. Conklin reported that no District staff was able to attend the OCWD
Groundwater Producers meeting on September 12. Meeting minutes
prepared by OCWD were provided and reviewed with the Committee.
3.7. Status Report on Capital Projects in Progress
Mr. Conklin reported on capital projects in planning, design and
construction.
3.8. Status of Strategic Plan Initiatives
Mr. Conklin reported on the status of strategic plan initiatives relating to
engineering and operations.
3.9. Future Agenda Items and Staff Tasks
The Committee asked for a status report on the meter program, as noted
in Item 3.1 above.
4. ADJOURNMENT
4.1. The meeting adjourned at 4:40 p.m. The next meeting of the Planning-
Engineering-Operations Committee will be held Thursday, November 1,
2012 at 3:00 p.m.
4