HomeMy WebLinkAbout2009-04-02 - Planning-Engineering-Operations Committee Meeting Minutes
ITEM NO. /mod
MINUTES OF THE
YORBA LINDA WATER DISRICT
PLANNING-ENGINEERING-OPERATIONS COMMITTEE MEETING
April 2, 2009
A meeting of the Planning-Engineering-Operations Committee was called to order by
Director Mills at 4:00 p.m. The meeting was held at the District's Administrative Office
at 1717 East Miraloma Avenue, Placentia CA 92870.
COMMITTEE STAFF
Director William R. Mills, Chair Ken Vecchiarelli, General Manager
Director Paul R. Armstrong Steve Conklin, Engineering Manager
Lee Cory, Operations Manager
Ken Mendum, Operations Superintendent
John DeCriscio, Chief Plant Operator
ACTION ITEMS
1. Change Order No. 6 for the Lakeview Reservoir Project.
Engineering Manager Steve Conklin reported that construction is approximately
95% complete; however, rain in February has delayed the site finish work in
progress. It was determined that due to the rain an additional 21 calendar-days
of work will be required. Following, discussion, the Committee supported
recommending approval of Change Order No. 6 adding 21 calendar-days to the
project completion schedule.
2. Professional Services Agreement Amendment for Environmental Compliance
Services for the Highland Reservoir Replacement Project.
Engineering Manager Conklin reported that as part of the Mitigated Negative
Declaration for CEQA compliance for the project, the District was required to
provide photographs and documentation of the 1911 reservoir before demolition,
to comply with the conditions for Historic American Engineering Records. He
indicated that there was a misunderstanding with the District's consultant for
environmental document preparation, BonTerra Consulting, and this task was not
included in their original work scope. Accordingly, it is requested that this task be
added as a contract amendment with BonTerra. Following discussion, the
Committee supported recommending that the Professional Services Agreement
with BonTerra Consulting be amended in the amount of $15,700 for additional
environmental services. Director Armstrong requested that a copy of the
completed report on the history of the original Highland Reservoir be provided to
the Yorba Linda Public Library, in addition to copies at the District.
3. Award of Geotechnical Engineering Services for the Hidden Hills Reservoir
Project.
Engineering Manager Conklin reported that the District solicited proposals from
five qualified geotechnical engineering firms for materials testing and
geotechnical site review during construction. Only two firms submitted
proposals, but both of those have worked for the District and are well-qualified to
1
do the work. Accordingly, engineering staff evaluated those proposals in
accordance with the District's proposal evaluation process. Following discussion,
the Committee supported recommending that a Professional Services Agreement
be authorized for Geotechnical Engineering Services with Leighton Consulting in
the amount of $94,558.
4. Resolution Supporting the Santa Ana River Watershed Integrated Regional
Water Management Plan.
Engineering Manager Conklin reported that the Santa Ana Watershed Project
Authority has released its draft Santa Ana River Watershed Integrated Regional
Water Management Plan (IRWMP), and is requesting a resolution of support and
a response letter for the work. The plan will be used to pursue grant funding
through Prop 84. Following discussion, the Committee recommended that the
Board adopt Resolution 09-05 supporting the IRWMP and its submittal to the
Department of Water Resources for Prop 84 funding.
5. Shapell Pre-Annexation Acreage Fee Agreement.
Engineering Manager Conklin reported that Shapell Industries requested the
preparation of an Acreage Fee Agreement for sewer projects that have since
been constructed and are working effectively. He noted that the work was
completed under letter agreements by staff no longer at Shapell and the District.
As such, new staff at Shapell requested that the letter agreements be
memorialized in an agreement for the record. An agreement was drafted by
Shapell, approved by District staff and legal counsel, and submitted to the
Committee for review and consideration. Following discussion, the Committee
recommended that the Board authorize execution of the Acreage Fee Agreement
with Shapell.
DISCUSSION ITEMS
6. Preliminary CIP Budget for 2009-14.
General Manager Ken Vecchiarelli and Engineering Manager Conklin presented
a first-draft list of Capital Improvement Projects proposed for the 2009 to 2014
time frame. Ken noted that by August 2010, an estimated $60 million of the $76
million in CIP projects listed for the 2007-12 time-frame will have completed
construction, with the remaining in planning, design and construction. The draft
CIP for 2009-2014 was briefly reviewed, and included planning studies, capital
facility replacement and refurbishment items, capital facility maintenance items,
and capital facility improvement items totaling $14.5 million. It was noted that
several of the items are very preliminary and require further refinement and
evaluation. Following discussion, the Committee asked staff to continue work on
the CIP plan and bring it back for further consideration.
7. Monthly Groundwater Production and Purchased Water Report.
Chief Plant Operator John DeCriscio presented the monthly report and described
our groundwater and import water purchases versus goals. As part of the
production documentation, John provided a new graph showing the cumulative
water supply values for the water year. He reported that the District remains on
track to achieve the BPP Goal of 52% and CUP production of 2166 AF.
2
8. Monthly Preventative Maintenance Program Report.
Operations Manager Lee Cory and Operations Superintendent Ken Mendum
reported on the status of the Preventative Maintenance Program to date. Ken
noted that we are close to our production goals in all catagories. The status of
sewer televising was noted at 93%, and its value to the District to help us be
proactive to address potential problems before they become stoppages and
overflows. The Committee asked that a summary be added to the monthly report
on repair of damaged sewer lines.
9. Monthly MWDOC Managers Meeting Summary Report.
General Manager Vecchiarelli reported on his attending the monthly meeting in
March. He noted that Met plans to increase the cost of imported water by 20% in
September 2009, and that the cost may increase by an additional 20% over the
next two years.
10. Monthly OC Groundwater Producers Meeting Summary Report.
Engineering Manager Conklin presented the report for the Groundwater
Producers meeting for March. He noted that OCWD plans to keep the
Replenishment Assessment at $249 per AF, and that the Basin Production
Assessment is planned to be approximately 64%. These values will be
confirmed by the OCWD Board in April. Ken Vecchiarelli also noted that OCWD
was looking at the possibility of prepurchasing water from Met at today's rate for
delivery at a future date. This is under discussion with Met staff.
11. Status Report on Capital Projects in Progress.
Steve Conklin presented the Status Report on Capital Projects for March 2009.
12. Plan for Expansion of Groundwater Supply.
In Agenda Items 6 and 11, plans for new wells 20 and 21 in the current budget,
and future wells 22 to 25 were discussed. In Agenda Item 12, Ken Vecchiarelli
further emphasized the critical importance of constructing new wells, to replace
aging wells and to expand our groundwater production. Ken and John DeCriscio
presented a graph titled "YLWD Groundwater Production vs. OCWD BPP." The
graph shows the District's progress in recent years increasing groundwater
production, and how that compares to our allowable production per the BPP. It
was noted that we are producing at the limit of our facilities and that additional
wells and improvements at the Highland Booster Station are needed to further
increase production. Ken reported that staff is working on both of these needs.
13. Future Agenda Items and Staff Tasks.
Director Mills asked about the District's per-capita water use and does it include
use by the City and schools. Ken Vecchiarelli noted that it can be determined
various ways. For residential use, he confirmed that it is approximately 216
gallons per capita per day per the most recent determination. Director Mills also
asked about the Community Advisory Committee meeting on March 31. Ken
Vecchiarelli provided a short summary and noted that the next meeting will be
April 6.
ADJOURNMENT
The Committee adjourned at 5:50 p.m. The next meeting of the Planning-Engineering-
Operations Committee will be held May 7, 2009 at 4:00 p.m.
3