HomeMy WebLinkAbout2008-04-03 - Planning-Engineering-Operations Committee Meeting Minutes
ITEM NO. ?4-
APPROVED BY THE BOARD OF DIRECTORS
MINUTES OF THE OF THE YORBA LINDA WATER DISTRICT
YORBA LINDA WATER DISTRICT APR 1_
PLANNING-ENGINEERING-OPERATIONS COMMITTEE
April 3, 2008
Y
A meeting of the Planning-Engineering-Operations Committee was called to order by
Committee Chair William Mills at 8:30 a.m. The meeting was held at the District
Administrative Offices at 4622 Plumosa Drive, Yorba Linda.
DIRECTORS PRESENT: STAFF PRESENT:
William R. Mills, Chairman Mike Payne, General Manager
Paul R. Armstrong, Director Ken Vecchiarelli, Assistant GM
Lee Cory, Operations Manager
Ken Mendum, Operations Superintendent
John DeCriscio, Chief Plant Operator
Diane Dalton, Sr. Maintenance Dist. Operator
VISITORS PRESENT:
Mr. Jack Santos, representing Mt. San Antonio Home Owners Association
Mr. Gordon Thompson, representing the King Family Development
Mr. Fred Cornwell, engineer for the King Family Development project
DISCUSSION ITEMS (Items were discussed out of order from the posted a4enda):
1. Furnace Creek Sewer Lining. Ms. Dalton and Mr. Mendum reported on a sewer main
repair within an easement in the Locke Ranch Service Area between Furnace Creek
Road and Amberdale Drive. The repairs were performed using a trenchless slip lining
technology. Crews inserted a flexible fiber-reinforced liner inside the damaged sewer
main from a manhole located in a landscaped slope on a private property. The repairs
were performed with no excavation and with no property damage or landscaping
reconstruction required. Once in place, the liner is expanded using steam to form a
tight bond against the inside of the sewer pipe bridging any gaps and cracks and
restoring the integrity and smooth channel flow.
2. Preventative Maintenance Program Status Report. Mr. Mendum and Mr. Cory
reported on the monthly maintenance activities and presented the updated
spreadsheet tracking progress of these efforts. Mr. Mendum reported where he was
projecting progress to be on or ahead of schedule and which efforts he thought would
require a more focused effort to finish the year on target with goals and objectives
established at the beginning of the fiscal year.
3. Status Report on Meter Replacement and Radio Read Retrofit Project. Mr. Mendum
reported on these efforts and showed where he would take crews that completed
other maintenance duties ahead of schedule to pick up the pace of the meter
replacement and retrofit program. The goal is to get the Western Service Area
completely converted to radio read meters by the end of Fiscal Year 2008-09. Mr.
Mendum and Ms. Dalton left the meeting following these discussions.
-1-
4. Terms and Conditions for Water Service for the King Family Development. Messrs.
Santos, Thompson and Cornwell had all joined the meeting by this time to discuss a
tentative project extending north of the newly developed Casino Ridge. The 11 lot
development had previously approved Terms and Conditions (T&C's) for Water
Service, which were approved in 2003 but which had subsequently expired.
Woodbridge Development has since completed a 67 lot development extending from
San Antonio Road up Casino Ridge consisting of private streets maintained by the Mt.
San Antonio Home Owners Association (HOA). Mr. Vecchiarelli reported on the
circumstances that have changed since the 2003 T&C's were approved including the
adoption of higher standards for service pressures and more stringent water storage
criteria. These standards were adopted with the 2005 Domestic Water System Master
Plan and create a problem for several of the pads in the proposed King Family
Development, which were designed at or near 100 feet below the high water level of
the reservoir serving the property. Mr. Vecchiarelli and Mr. Cornwell discussed the
limitations for grading within the King Family Property due to the location of two
existing 36-inch diameter high pressure gas mains. The committee discussed the
complications that this development would encounter in trying to meet the District's
newer standards for service and encouraged staff and the developers to work together
to find acceptable alternatives for the Committee and ultimately the Board of Directors
to consider. Mr. Santos, representing the HOA, presented a letter stating their
concerns about the proposed development extending the private streets and utilities
and questioned the affects of this development on the service levels to the existing
community. All visitors left the meeting following this discussion.
5. Monthly Water Production and Purchased Imports through March 2008. Chief Plant
Operator DeCriscio presented the report for February and March. The groundwater
production percentage for the year is tracking below allowable numbers (the Basin
Production Percentage or BPP) due to the failure of an old temporary highline to
Fairmont Boulevard. This pipeline broke in late January causing damage to adjacent
properties. The pipeline has been repaired several times but has surpassed its useful
life expectancy and represents a liability. The permanent pipeline is currently under
construction in Bastanchury Road and should be completed and placed in service by
the end of April. Staff anticipates making up some of the production percentage gap
in May and June by utilizing the additional capacity from the new Lakeview Booster
Pump Station once the new 18-inch pipeline becomes operational in Bastanchury
Road from Lakeview to Fairmont Boulevard. Mr. DeCriscio and Mr. Cory left the
meeting following this discussion.
ACTION ITEMS:
6. Construction Agreement for the Highland Reservoir Replacement Project. The
Committee discussed staffs recommendation for award of a construction agreement
to Schuler Engineering, the lowest responsive and responsible bidder. This matter is
included as an action item for the Board of Directors' consideration in this agenda
packet.
-2-
DISCUSSION ITEMS (Continued):
7. Change Order No. 1 to SSC Construction, Inc. The Committee discussed staffs
recommendation for approval of a negotiated settlement related to a delayed notice to
proceed. SSC, staff and legal counsel negotiated a settlement incorporated as
Change Order No. 1 to the construction agreement with SSC. This matter is included
as an action item for the Board of Directors' consideration in this agenda packet.
8. Monthly MWDOC Managers Meeting. No report was given since Mr. Cory who
attended the MWDOC Managers Meeting had left the Planning-Engineering-
Operations Committee meeting.
9. Monthly Orange County Groundwater Producers Meeting. Mr. Vecchiarelli reported
on the monthly meeting of the GW Producer's Group held March 12, 2008 and
discussed activities related to the OCWD budget process.
10. Status Report of Capital Improvement Projects in Progress. No report was given.
ADJOURNMENT:
The Committee adjourned at 9:55 a.m. The next regularly scheduled Planning-
Engineering-Operations Committee will be held May 1, 2008 at the new administration
building located at 1717 E. Miraloma Avenue, Placentia.
-3-